Difference between revisions of "Place du Portage III AWR Notices to tenants/occupants"

From wiki
Jump to navigation Jump to search
Line 33: Line 33:
 
!'''Release Date'''
 
!'''Release Date'''
 
!'''Purpose'''
 
!'''Purpose'''
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/5/52/CN38.1_Structural_Steel_Upgrades_in_Laurier-Tach%C3%A9_Parking_Garage.F.pdf Tower Crane 2 (TC-2): Structural Steel Upgrades (UPDATED)]'''
 +
|November 25, 2022
 +
 +
|To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
 
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/8/81/CN29.1_Tower_Crane_Installation-Laurier-Tach%C3%A9ParkingGarage.F.pdf Tower Crane Installation in Laurier-Taché Parking Garage (UPDATED)]'''
 
|'''[https://wiki.gccollab.ca/images/8/81/CN29.1_Tower_Crane_Installation-Laurier-Tach%C3%A9ParkingGarage.F.pdf Tower Crane Installation in Laurier-Taché Parking Garage (UPDATED)]'''
Line 88: Line 93:
 
   
 
   
 
|To delineate the construction space required to install the shear wall for PDP III Tower C as part of the PDP3 AWR Project.
 
|To delineate the construction space required to install the shear wall for PDP III Tower C as part of the PDP3 AWR Project.
|-
 
|'''[https://wiki.gccollab.ca/images/5/5e/CN38_Structural_Steel_Upgrades_in_Laurier-Tach%C3%A9_Parking_Garage.F.pdf Tower Crane 2 (TC-2): Structural Steel Upgrades]'''
 
|October 27, 2022
 
 
|To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
 
 
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/7/77/CN-36_Domestic_Water_Service_Interruption_R3.pdf Temporary Disruption of Domestic Water Supply On Emergency Basis]'''
 
|'''[https://wiki.gccollab.ca/images/7/77/CN-36_Domestic_Water_Service_Interruption_R3.pdf Temporary Disruption of Domestic Water Supply On Emergency Basis]'''

Revision as of 10:59, 28 November 2022

PDP3 Welcome Page1.jpg


Français


Project overview Project phases and milestones Objectives and benefits Notices to building occupants More information

Notices to tenants/occupants


Tenants of PDP3 and adjacent buildings have been informed of construction work through operational notices issued by BGIS, with PSPC’s informal consent. Notices issued to date are provided below. This list will be updated regularly.

Title (link) Release Date Purpose
Tower Crane 2 (TC-2): Structural Steel Upgrades (UPDATED) November 25, 2022 To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
Tower Crane Installation in Laurier-Taché Parking Garage (UPDATED) November 25, 2022 To prepare the site for the construction and installation of the tower crane (TC-2).
Temporary Shutdown of Primary Chilled Water Loop (UPDATED) November 25, 2022 To directly reconnect critical mechanical equipment (V-30, V-72 and V-74) to the primary chilled water loop to accommodate the demolition of the pumps and heat exchangers in Tower C Level 02. Space in the mechanical room is required for construction of the concrete shear wall and associated re-shoring.
Tower C: Emergency Generator Removal November 18, 2022 To disconnect the Tower C generator and then reconnect its emergency load to the generator control panel in Tower B to ensure backup electricity in the event of an electrical power outage.
Tower B1 - Level 0: Construction Hoarding November 17, 2022 To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
Towers B1 & B3: Demolition and Construction Activities (L1, L2 & L3) November 17, 2022 To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
Towers B1 & B3: Demolition and Construction Activities (L6 to L12) November 17, 2022 To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
Tower B: Exterior Demolition November 17, 2022 To install temporary new stairs to allow emergency access and egress during construction activities and demolish existing stairs.
Construction of Safety Orientation Room November 14, 2022 To create an orientation room outside of the construction zone for the purpose of performing heath and safety orientations as part of the Place du Portage III AWR Project.
Place du Centre: Temporary Closure of Access Route to Loading Dock November 4, 2022 To allow space to park a 90-Ton crane and assist with the installation of overhead protection.
Asbestos Abatement in Tower B1 (L3) October 31, 2022 To prepare the site for a new set of doors and to allow a new passage to the freight elevator in Tower A.
Delineation and Hoarding Wall in Mechanical Room October 28, 2022 To delineate the construction space required to install the shear wall for PDP III Tower C as part of the PDP3 AWR Project.
Temporary Disruption of Domestic Water Supply On Emergency Basis October 21, 2022 The main objective of the domestic water shutdown is due to concerns over the integrity of the pipe, and is required to allow for the reinforcement of the primary city water feed to Tower C ahead of excavation. This request is based on the emergency basis to replace Isolation valve of the fire suppression system.
Tower A: Asbestos Abatement in Swing Spaces for Critical Tenants' Operations (L15) October 19, 2022 To prepare the interim space for Tower B occupants.
Erection of Tower Crane (TC-1) in the construction area between PDP3 and PDP4 (Woodlands area) October 11, 2022 The erection of the tower crane (TC-1) is one of the PDP3 AWR Project milestones as it visually symbolizes the beginning of the demolition activities.
Towers A & B: Delineation and Hoarding Wall (L1, L2 and L3) September 26, 2022 To outline and separate the occupied space in Tower A2 from the construction activities in Tower B1.
Tower B: Exterior Demolition September 20, 2022 To install temporary new stairs to allow, emergency access and egress during construction activities, and the demolition of the existing stairs. These enabling work activities are required to set up the ElissDon laydown area for construction.
Bicycle Enclosure Relocation September 6, 2022 To facilitate the additional site logistics required for the Construction Manager to install exterior hoarding in preparation for construction work around PDP III Tower C.
Towers C and D Closure: Pedestrians Wayfinding Plans (Exterior) September 6, 2022 How to circulate between PDP4 and the A/B/E towers of PDP3 (exterior).
Towers C and D Closure: Pedestrians Wayfinding Plans (Interior) September 6, 2022 How to circulate between PDP4 and the A/B/E towers of PDP3 (interior).
Removal of Trees and Shrubs August 22, 2022 To prepare the area for the upcoming construction of the curtain wall mockup.
Sidewalk Closure: Laurier Street August 16, 2022 To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
Traffic Lane Closure: Laurier Street August 16, 2022 To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
PDP IV: Sign replacement August 15, 2022 To install the new PDP IV sign onto the exterior corner of the building, next to the Woodlands Area.
Mission Critical Spaces August 2, 2022 To complete A1 and A2 Towers construction fit up, to accommodate B1 Tower tenants.
Place du Portage IV: Wayfinding August 2, 2022 To facilitate the construction renovations, including the Tower C Curtainwall Upgrades; Tower C Interior Upgrades; and Structural Upgrades for the Place du Portage AWR Project.
Towers A & B: Delineation and Hoarding Wall August 2, 2022 To outline and separate the occupied space in Tower A2 from the construction activities in Tower B1.
Temporary Partial Closure: Laurier-Taché Parking Garage August 2, 2022 To facilitate the following renovations: installation of a new elevator pit; an interruption in the ventilation system; structural upgrades; and replacement of underground piping.
Hoarding Wall: Tower B Exterior July 29, 2022 To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
Tower A and B Delineation Hoarding July 14, 2022 Outline and separate the occupied space in Tower A2 from the construction activities in Tower B1.
Interim Mailroom Demolition and Abatement July 14, 2022 See notice
Interim Mailroom Construction June 20, 2022 See notice.
Sidewalk and Lane Closure on Maisonneuve Boulevard May 24, 2022 To facilitate the additional site logistics required for the CM and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
Construction Hoarding: Tower C - North Courtyard May 24, 2022 To facilitate the additional site logistics required for the Construction Manager and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
Construction Hoarding: Tower B - Exterior May 24, 2022 To facilitate the additional site logistics required for the Construction Manager and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
Construction hoarding activities April 6, 2022 The main objective of the construction hoarding activities is to create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
Environmental Soil Study Characterization April 5, 2022 To help identify potential contaminants in the soil in and around the project area. Information gathered during this work will help describe the environmental quality of the soil.
Tree Removal Activities March 25, 2022 To facilitate additional site logistics requirements for the Construction Manager (CM) to enable construction related activities in preparation of the PDP3 AWR Project and to update the landscape and riverfront greenbelt in connection to the complex.
Construction hoarding activities (Interim space) February 22, 2022 To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
Construction hoarding (CM site) February 17, 2022 To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
Construction hoarding February 11, 2022 To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
Tree removal activities (Woodland Area) February 9, 2022 To create an interim construction laydown area for the CM to enable construction related activities in preparation of the PDP3 AWR Project; and an opportunity to update the landscape and Riverfront Greenbelt connection to the complex.


Back to Welcome Page