Difference between revisions of "Place du Portage III AWR Notices to tenants/occupants"
Jump to navigation
Jump to search
Line 34: | Line 34: | ||
!'''Purpose''' | !'''Purpose''' | ||
|- | |- | ||
− | |'''[https://wiki.gccollab.ca/images/3/3a/CN54.1_Tower_D_and_E_Delineation_Hoarding.F2.pdf Towers D & E: Delineation and Hoarding Wall]''' | + | |'''[https://wiki.gccollab.ca/images/3/3a/CN54.1_Tower_D_and_E_Delineation_Hoarding.F2.pdf Towers D & E: Delineation and Hoarding Wall (UDPATED)]''' |
|January 18, 2022 | |January 18, 2022 | ||
Revision as of 11:45, 18 January 2023
Français |
Project overview | Project phases and milestones | Objectives and benefits | Notices to building occupants | More information |
Notices to tenants/occupants
Tenants of PDP3 and adjacent buildings have been informed of construction work through operational notices issued by BGIS, with PSPC’s informal consent. Notices issued to date are provided below. This list will be updated regularly.
Title (link) | Release Date | Purpose |
---|---|---|
Towers D & E: Delineation and Hoarding Wall (UDPATED) | January 18, 2022 | To outline and separate the occupied space from the demolition and abatement activities. |
Tower B1: Delineation and Hoarding Wall (UPDATED) | January 17, 2022 | To outline and separate the occupied space from the demolition and abatement activities. |
Tower E: Construction of Partition Wall | January 6, 2023 | To outline and separate the occupied space from the bulk of demolition and abatement activities while the Security Operations Centre remains in place (02B2-101). |
Tower A: Storm and Sanitary Pipe Installation | January 4, 2023 | To demolish the existing pipe and reinstall a new underground sanitary and storm one in L03 (A0314) in Tower A. |
Temporary Disruption to the Laurier-Taché Parking Garage Door Operators | January 3, 2023 | To remove, then relocate the fiber optic cables, including conduits and boxes that control the garage door openers within the Laurier-Taché parking garage. The conduits and boxes are currently located in L02 in Tower C on a block wall that is scheduled to be demolished. |
Opening of Interim Mailroom | December 19, 2022 | To move the mailroom occupants from the old location in Tower B3 to the new location in Tower B2.
Note: The old mailroom location is scheduled for demolition as part of phase 1 of the PDP3 AWR Project. |
Tower B: Exterior Demolition (UPDATED) | December 19, 2022 | To install temporary new stairs to allow emergency access and egress during construction activities and demolish existing stairs. |
Preparation of the Mobile Crane Base | December 14, 2022 | To prepare the base, a granular pad, for the installation of the mobile crane on Laurier Street, which is to assist with the installation of the Tower Crane (TC-2) within the exterior construction zone of Tower B. |
Tower C: Removal of Emergency Generator | December 2, 2022 | To disconnect Tower C generator and then reconnect the feeds to the generators in Towers A and B to ensure backup electricity in the event of an electrical power outage. |
Installation and Mobilization of Mast Climbers | December 2, 2022 | To assist in the removal of the exterior envelope of Towwers C1/C2. |
Tower Crane 2 (TC-2): Structural Steel Upgrades (UPDATED) | November 25, 2022 | To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3. |
Tower Crane Installation in Laurier-Taché Parking Garage (UPDATED) | November 25, 2022 | To prepare the site for the construction and installation of the tower crane (TC-2). |
Temporary Shutdown of Primary Chilled Water Loop (UPDATED) | November 25, 2022 | To directly reconnect critical mechanical equipment (V-30, V-72 and V-74) to the primary chilled water loop to accommodate the demolition of the pumps and heat exchangers in Tower C Level 02. Space in the mechanical room is required for construction of the concrete shear wall and associated re-shoring. |
Tower C: Emergency Generator Removal | November 18, 2022 | To disconnect the Tower C generator and then reconnect its emergency load to the generator control panel in Tower B to ensure backup electricity in the event of an electrical power outage. |
Tower B1 - Level 0: Construction Hoarding (UPDATED) | November 17, 2022 | To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project. |
Towers B1 & B3: Demolition and Construction Activities (L1, L2 & L3) | November 17, 2022 | To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations. |
Towers B1 & B3: Demolition and Construction Activities (L6 to L12) | November 17, 2022 | To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations. |
Place du Centre: Temporary Closure of Access Route to Loading Dock | November 4, 2022 | To allow space to park a 90-Ton crane and assist with the installation of overhead protection. |
Asbestos Abatement in Tower B1 (L3) | October 31, 2022 | To prepare the site for a new set of doors and to allow a new passage to the freight elevator in Tower A. |
Delineation and Hoarding Wall in Mechanical Room | October 28, 2022 | To delineate the construction space required to install the shear wall for PDP III Tower C as part of the PDP3 AWR Project. |
Temporary Disruption of Domestic Water Supply On Emergency Basis | October 21, 2022 | The main objective of the domestic water shutdown is due to concerns over the integrity of the pipe, and is required to allow for the reinforcement of the primary city water feed to Tower C ahead of excavation. This request is based on the emergency basis to replace Isolation valve of the fire suppression system. |
Tower A: Asbestos Abatement in Swing Spaces for Critical Tenants' Operations (L15) | October 19, 2022 | To prepare the interim space for Tower B occupants. |
Erection of Tower Crane (TC-1) in the construction area between PDP3 and PDP4 (Woodlands area) | October 11, 2022 | The erection of the tower crane (TC-1) is one of the PDP3 AWR Project milestones as it visually symbolizes the beginning of the demolition activities. |
Towers A & B: Delineation and Hoarding Wall (L1, L2 and L3) | September 26, 2022 | To outline and separate the occupied space in Tower A2 from the construction activities in Tower B1. |
Bicycle Enclosure Relocation | September 6, 2022 | To facilitate the additional site logistics required for the Construction Manager to install exterior hoarding in preparation for construction work around PDP III Tower C. |
Towers C and D Closure: Pedestrians Wayfinding Plans (Exterior) | September 6, 2022 | How to circulate between PDP4 and the A/B/E towers of PDP3 (exterior). |
Towers C and D Closure: Pedestrians Wayfinding Plans (Interior) | September 6, 2022 | How to circulate between PDP4 and the A/B/E towers of PDP3 (interior). |
Removal of Trees and Shrubs | August 22, 2022 | To prepare the area for the upcoming construction of the curtain wall mockup. |
Sidewalk Closure: Laurier Street | August 16, 2022 | To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls. |
Traffic Lane Closure: Laurier Street | August 16, 2022 | To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls. |
PDP IV: Sign replacement | August 15, 2022 | To install the new PDP IV sign onto the exterior corner of the building, next to the Woodlands Area. |
Mission Critical Spaces | August 2, 2022 | To complete A1 and A2 Towers construction fit up, to accommodate B1 Tower tenants. |
Place du Portage IV: Wayfinding | August 2, 2022 | To facilitate the construction renovations, including the Tower C Curtainwall Upgrades; Tower C Interior Upgrades; and Structural Upgrades for the Place du Portage AWR Project. |
Towers A & B: Delineation and Hoarding Wall | August 2, 2022 | To outline and separate the occupied space in Tower A2 from the construction activities in Tower B1. |
Temporary Partial Closure: Laurier-Taché Parking Garage | August 2, 2022 | To facilitate the following renovations: installation of a new elevator pit; an interruption in the ventilation system; structural upgrades; and replacement of underground piping. |
Hoarding Wall: Tower B Exterior | July 29, 2022 | To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is to ensure the safety and protection of the public and to contain the construction site within the hoarding walls. |
Tower A and B Delineation Hoarding | July 14, 2022 | Outline and separate the occupied space in Tower A2 from the construction activities in Tower B1. |
Interim Mailroom Demolition and Abatement | July 14, 2022 | See notice |
Interim Mailroom Construction | June 20, 2022 | See notice. |
Sidewalk and Lane Closure on Maisonneuve Boulevard | May 24, 2022 | To facilitate the additional site logistics required for the CM and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls. |
Construction Hoarding: Tower C - North Courtyard | May 24, 2022 | To facilitate the additional site logistics required for the Construction Manager and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls. |
Construction Hoarding: Tower B - Exterior | May 24, 2022 | To facilitate the additional site logistics required for the Construction Manager and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls. |
Construction hoarding activities | April 6, 2022 | The main objective of the construction hoarding activities is to create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project. |
Environmental Soil Study Characterization | April 5, 2022 | To help identify potential contaminants in the soil in and around the project area. Information gathered during this work will help describe the environmental quality of the soil. |
Tree Removal Activities | March 25, 2022 | To facilitate additional site logistics requirements for the Construction Manager (CM) to enable construction related activities in preparation of the PDP3 AWR Project and to update the landscape and riverfront greenbelt in connection to the complex. |
Construction hoarding activities (Interim space) | February 22, 2022 | To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project. |
Construction hoarding (CM site) | February 17, 2022 | To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project. |
Construction hoarding | February 11, 2022 | To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project. |
Tree removal activities (Woodland Area) | February 9, 2022 | To create an interim construction laydown area for the CM to enable construction related activities in preparation of the PDP3 AWR Project; and an opportunity to update the landscape and Riverfront Greenbelt connection to the complex. |