Difference between revisions of "NTTO test"
m |
(Added RI Summary.) |
||
Line 1: | Line 1: | ||
− | |||
This is a test page for NTTO. | This is a test page for NTTO. | ||
− | ALL RI CALENDARS DISPLAYED ARE OUT OF DATE AND ARE PRIMARILY USED FOR TESTING PURPOSES OF THIS SITE. | + | ALL RI CALENDARS DISPLAYED ARE OUT OF DATE AND ARE PRIMARILY USED FOR TESTING PURPOSES OF THIS SITE.[[File:RI-Calendar-Webpart-2019-06-03.png|border|center|907x907px]] |
[[File:RI-Calendar-Webpart-2019-05-10.png|thumb|test]] | [[File:RI-Calendar-Webpart-2019-05-10.png|thumb|test]] | ||
+ | {| class="wikitable" | ||
+ | |+ | ||
+ | !RI | ||
+ | !Scope | ||
+ | !Deployment Date | ||
+ | !Milestone Dates | ||
+ | !Testing Resources | ||
+ | !Comments | ||
+ | |- | ||
+ | |'''24.1.1''' | ||
+ | |URP-IV (2.3.1) | ||
+ | |June 18, 2019 | ||
+ | |1. Integration/UAT: now-June 17, 2019 | ||
+ | |1. NTTO/PSD | ||
+ | |Synopsis: URP IV upgrade. Enhancements to IV to accommodate S-band radars. This is the 12.04 version. The 18.04 version will be deployed with IFWUU. | ||
+ | |||
+ | RI Notes: Testing in progress on RI testing IFW's. Here is a summary of the changes: | ||
+ | |||
+ | • Animation improvements for products with different time increments – specifically for S-band radars (Mantis 20364, 19683) | ||
+ | |||
+ | • Bug fix: CELL VIEW window launched from IV SCIT sometimes loads with no data. This can also result in IV loop lock. (Mantis 20510) | ||
+ | |- | ||
+ | |'''24.2''' | ||
+ | |Aviation Changes | ||
+ | |June 20, 2019 | ||
+ | |Testing completed. | ||
+ | | | ||
+ | |Synopsis: wxapps program changes... | ||
+ | |||
+ | <nowiki>http://msc-mantis.to.on.ec.gc.ca/mantis/view.php?id=20779</nowiki> | ||
+ | |||
+ | <nowiki>http://msc-mantis.to.on.ec.gc.ca/mantis/view.php?id=20776</nowiki> | ||
+ | |||
+ | RI Notes: Testing completed. We are ready to deploy. | ||
+ | |- | ||
+ | |'''24.X''' | ||
+ | |URP 2.13.1 | ||
+ | |July 23, 2019 | ||
+ | |Package submission: June 21, 2019 | ||
+ | |||
+ | 1. Beta: now - June 20 | ||
+ | |||
+ | 2. Integration: June 24-28 | ||
+ | |||
+ | 3. UAT: July 2-22 | ||
+ | |1. URP dev team | ||
+ | |||
+ | 2. NTTO | ||
+ | |||
+ | 3. PSD | ||
+ | |Synopsis: Change details included in Section C of RFI: <nowiki>https://ecollab.ncr.int.ec.gc.ca/theme/165/RFI/CIC-2019-RFI014-URP-2_13.docx</nowiki> | ||
+ | |||
+ | RI notes: Radar data for temporary X-band radars will not be available in IV until later in summer. | ||
+ | |- | ||
+ | |'''24.X''' | ||
+ | |Upgrade wxapps servers to 18.04 | ||
+ | |July 16-17, 2019 | ||
+ | |1. Test wxapps-beta servers: June 19-28, 2019 | ||
+ | |||
+ | 2. Test wxapps-stage servers: June 28-July 12, 2019 | ||
+ | |1. PSD: 2 (2d) | ||
+ | |||
+ | 2. PSD: 2 (1d) | ||
+ | |Synopsis: Upgrade WxApps servers to Ubuntu 18.04. | ||
+ | |||
+ | RI Notes: 18.04 components have been submitted: Components-WxApps.xlsx. There has been some delay in building 18.04 wxapps-beta servers. | ||
+ | |- | ||
+ | |'''24.X''' | ||
+ | |Aviation Changes | ||
+ | |August 15, 2019 | ||
+ | |TBD | ||
+ | |TBD | ||
+ | |Synopsis: Aviation program changes. | ||
+ | |||
+ | RI Notes: NTTO are awaiting RFI submission. | ||
+ | |- | ||
+ | |'''24.X''' | ||
+ | |IFW Ubuntu Upgrade (IFWUU) | ||
+ | |Sep 10-12, 2019 | ||
+ | |1. Creation of ops and non-ops testing IFW is each office: now-July 8, 2019 | ||
+ | |||
+ | 2. Live UAT on ops IFW: July 16 - Sep 9, 2019 | ||
+ | |1. NTTO and SSC | ||
+ | |||
+ | 2. As many forecasters as possible | ||
+ | |Synopsis: Upgrade of IFW from Ubuntu12.04 to 18.04. Includes renaming of all IFW's according to new national SSC standard and 18.04 release of URP-IV (to accommodate 6 minute S-band data). | ||
+ | |||
+ | RI Notes: This project has restarted but there is a risk of delay. First priority is to setup KDE 18.04 test environments in all offices. | ||
+ | |- | ||
+ | |'''25.0''' | ||
+ | |NinJo 3.4 (WPR1.5, Tsunami) + Scribe | ||
+ | |September 24, 2019 | ||
+ | |Scribe packages: June 19, 2019 (for Beta) | ||
+ | |||
+ | NinJo packages: July 10, 2019 (for Integration) | ||
+ | |||
+ | Beta: June 20-Jul 9, 2019 | ||
+ | |||
+ | Integration: Jul 16-Aug 16, 2019 | ||
+ | |||
+ | UAT: Aug 26-Sep 9, 2019 | ||
+ | |1. FSII only | ||
+ | |||
+ | 2. 1 (2d) | ||
+ | |||
+ | 3. 1 (3h) | ||
+ | |Synopsis: NinJo 3.4 MSC config release (including WPR-O Release 1.5 and deployment of Tsunami alerts in MWAS) plus changes to Scribe. | ||
+ | |||
+ | RI Notes: PSD testing resources required for Integration and UAT. | ||
+ | |- | ||
+ | |'''25.X''' | ||
+ | |Edigraf Ubuntu Upgrade | ||
+ | |September 2019 | ||
+ | |TBD | ||
+ | |TBD | ||
+ | |Synopsis: Upgrade of Edigraf to Ubuntu 18.04 | ||
+ | |||
+ | RI Notes: In RI planning phase only. Project information can be found at: <nowiki>http://dvwiki.science.gc.ca/wiki/Edigraf_port_project</nowiki> | ||
+ | |- | ||
+ | |'''None''' | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | |- | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | |- | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | | | ||
+ | |} |
Revision as of 15:19, 17 June 2019
This is a test page for NTTO.
ALL RI CALENDARS DISPLAYED ARE OUT OF DATE AND ARE PRIMARILY USED FOR TESTING PURPOSES OF THIS SITE.
RI | Scope | Deployment Date | Milestone Dates | Testing Resources | Comments |
---|---|---|---|---|---|
24.1.1 | URP-IV (2.3.1) | June 18, 2019 | 1. Integration/UAT: now-June 17, 2019 | 1. NTTO/PSD | Synopsis: URP IV upgrade. Enhancements to IV to accommodate S-band radars. This is the 12.04 version. The 18.04 version will be deployed with IFWUU.
RI Notes: Testing in progress on RI testing IFW's. Here is a summary of the changes: • Animation improvements for products with different time increments – specifically for S-band radars (Mantis 20364, 19683) • Bug fix: CELL VIEW window launched from IV SCIT sometimes loads with no data. This can also result in IV loop lock. (Mantis 20510) |
24.2 | Aviation Changes | June 20, 2019 | Testing completed. | Synopsis: wxapps program changes...
http://msc-mantis.to.on.ec.gc.ca/mantis/view.php?id=20779 http://msc-mantis.to.on.ec.gc.ca/mantis/view.php?id=20776 RI Notes: Testing completed. We are ready to deploy. | |
24.X | URP 2.13.1 | July 23, 2019 | Package submission: June 21, 2019
1. Beta: now - June 20 2. Integration: June 24-28 3. UAT: July 2-22 |
1. URP dev team
2. NTTO 3. PSD |
Synopsis: Change details included in Section C of RFI: https://ecollab.ncr.int.ec.gc.ca/theme/165/RFI/CIC-2019-RFI014-URP-2_13.docx
RI notes: Radar data for temporary X-band radars will not be available in IV until later in summer. |
24.X | Upgrade wxapps servers to 18.04 | July 16-17, 2019 | 1. Test wxapps-beta servers: June 19-28, 2019
2. Test wxapps-stage servers: June 28-July 12, 2019 |
1. PSD: 2 (2d)
2. PSD: 2 (1d) |
Synopsis: Upgrade WxApps servers to Ubuntu 18.04.
RI Notes: 18.04 components have been submitted: Components-WxApps.xlsx. There has been some delay in building 18.04 wxapps-beta servers. |
24.X | Aviation Changes | August 15, 2019 | TBD | TBD | Synopsis: Aviation program changes.
RI Notes: NTTO are awaiting RFI submission. |
24.X | IFW Ubuntu Upgrade (IFWUU) | Sep 10-12, 2019 | 1. Creation of ops and non-ops testing IFW is each office: now-July 8, 2019
2. Live UAT on ops IFW: July 16 - Sep 9, 2019 |
1. NTTO and SSC
2. As many forecasters as possible |
Synopsis: Upgrade of IFW from Ubuntu12.04 to 18.04. Includes renaming of all IFW's according to new national SSC standard and 18.04 release of URP-IV (to accommodate 6 minute S-band data).
RI Notes: This project has restarted but there is a risk of delay. First priority is to setup KDE 18.04 test environments in all offices. |
25.0 | NinJo 3.4 (WPR1.5, Tsunami) + Scribe | September 24, 2019 | Scribe packages: June 19, 2019 (for Beta)
NinJo packages: July 10, 2019 (for Integration) Beta: June 20-Jul 9, 2019 Integration: Jul 16-Aug 16, 2019 UAT: Aug 26-Sep 9, 2019 |
1. FSII only
2. 1 (2d) 3. 1 (3h) |
Synopsis: NinJo 3.4 MSC config release (including WPR-O Release 1.5 and deployment of Tsunami alerts in MWAS) plus changes to Scribe.
RI Notes: PSD testing resources required for Integration and UAT. |
25.X | Edigraf Ubuntu Upgrade | September 2019 | TBD | TBD | Synopsis: Upgrade of Edigraf to Ubuntu 18.04
RI Notes: In RI planning phase only. Project information can be found at: http://dvwiki.science.gc.ca/wiki/Edigraf_port_project |
None | |||||