| This is a test page for NTTO. | | This is a test page for NTTO. |
| | | |
− | ALL RI CALENDARS DISPLAYED ARE OUT OF DATE AND ARE PRIMARILY USED FOR TESTING PURPOSES OF THIS SITE. | + | ALL RI CALENDARS DISPLAYED ARE OUT OF DATE AND ARE PRIMARILY USED FOR TESTING PURPOSES OF THIS SITE.[[File:RI-Calendar-Webpart-2019-06-03.png|border|center|907x907px]] |
| [[File:RI-Calendar-Webpart-2019-05-10.png|thumb|test]] | | [[File:RI-Calendar-Webpart-2019-05-10.png|thumb|test]] |
| + | {| class="wikitable" |
| + | |+ |
| + | !RI |
| + | !Scope |
| + | !Deployment Date |
| + | !Milestone Dates |
| + | !Testing Resources |
| + | !Comments |
| + | |- |
| + | |'''24.1.1''' |
| + | |URP-IV (2.3.1) |
| + | |June 18, 2019 |
| + | |1. Integration/UAT: now-June 17, 2019 |
| + | |1. NTTO/PSD |
| + | |Synopsis: URP IV upgrade. Enhancements to IV to accommodate S-band radars. This is the 12.04 version. The 18.04 version will be deployed with IFWUU. |
| + | |
| + | RI Notes: Testing in progress on RI testing IFW's. Here is a summary of the changes: |
| + | |
| + | • Animation improvements for products with different time increments – specifically for S-band radars (Mantis 20364, 19683) |
| + | |
| + | • Bug fix: CELL VIEW window launched from IV SCIT sometimes loads with no data. This can also result in IV loop lock. (Mantis 20510) |
| + | |- |
| + | |'''24.2''' |
| + | |Aviation Changes |
| + | |June 20, 2019 |
| + | |Testing completed. |
| + | | |
| + | |Synopsis: wxapps program changes... |
| + | |
| + | <nowiki>http://msc-mantis.to.on.ec.gc.ca/mantis/view.php?id=20779</nowiki> |
| + | |
| + | <nowiki>http://msc-mantis.to.on.ec.gc.ca/mantis/view.php?id=20776</nowiki> |
| + | |
| + | RI Notes: Testing completed. We are ready to deploy. |
| + | |- |
| + | |'''24.X''' |
| + | |URP 2.13.1 |
| + | |July 23, 2019 |
| + | |Package submission: June 21, 2019 |
| + | |
| + | 1. Beta: now - June 20 |
| + | |
| + | 2. Integration: June 24-28 |
| + | |
| + | 3. UAT: July 2-22 |
| + | |1. URP dev team |
| + | |
| + | 2. NTTO |
| + | |
| + | 3. PSD |
| + | |Synopsis: Change details included in Section C of RFI: <nowiki>https://ecollab.ncr.int.ec.gc.ca/theme/165/RFI/CIC-2019-RFI014-URP-2_13.docx</nowiki> |
| + | |
| + | RI notes: Radar data for temporary X-band radars will not be available in IV until later in summer. |
| + | |- |
| + | |'''24.X''' |
| + | |Upgrade wxapps servers to 18.04 |
| + | |July 16-17, 2019 |
| + | |1. Test wxapps-beta servers: June 19-28, 2019 |
| + | |
| + | 2. Test wxapps-stage servers: June 28-July 12, 2019 |
| + | |1. PSD: 2 (2d) |
| + | |
| + | 2. PSD: 2 (1d) |
| + | |Synopsis: Upgrade WxApps servers to Ubuntu 18.04. |
| + | |
| + | RI Notes: 18.04 components have been submitted: Components-WxApps.xlsx. There has been some delay in building 18.04 wxapps-beta servers. |
| + | |- |
| + | |'''24.X''' |
| + | |Aviation Changes |
| + | |August 15, 2019 |
| + | |TBD |
| + | |TBD |
| + | |Synopsis: Aviation program changes. |
| + | |
| + | RI Notes: NTTO are awaiting RFI submission. |
| + | |- |
| + | |'''24.X''' |
| + | |IFW Ubuntu Upgrade (IFWUU) |
| + | |Sep 10-12, 2019 |
| + | |1. Creation of ops and non-ops testing IFW is each office: now-July 8, 2019 |
| + | |
| + | 2. Live UAT on ops IFW: July 16 - Sep 9, 2019 |
| + | |1. NTTO and SSC |
| + | |
| + | 2. As many forecasters as possible |
| + | |Synopsis: Upgrade of IFW from Ubuntu12.04 to 18.04. Includes renaming of all IFW's according to new national SSC standard and 18.04 release of URP-IV (to accommodate 6 minute S-band data). |
| + | |
| + | RI Notes: This project has restarted but there is a risk of delay. First priority is to setup KDE 18.04 test environments in all offices. |
| + | |- |
| + | |'''25.0''' |
| + | |NinJo 3.4 (WPR1.5, Tsunami) + Scribe |
| + | |September 24, 2019 |
| + | |Scribe packages: June 19, 2019 (for Beta) |
| + | |
| + | NinJo packages: July 10, 2019 (for Integration) |
| + | |
| + | Beta: June 20-Jul 9, 2019 |
| + | |
| + | Integration: Jul 16-Aug 16, 2019 |
| + | |
| + | UAT: Aug 26-Sep 9, 2019 |
| + | |1. FSII only |
| + | |
| + | 2. 1 (2d) |
| + | |
| + | 3. 1 (3h) |
| + | |Synopsis: NinJo 3.4 MSC config release (including WPR-O Release 1.5 and deployment of Tsunami alerts in MWAS) plus changes to Scribe. |
| + | |
| + | RI Notes: PSD testing resources required for Integration and UAT. |
| + | |- |
| + | |'''25.X''' |
| + | |Edigraf Ubuntu Upgrade |
| + | |September 2019 |
| + | |TBD |
| + | |TBD |
| + | |Synopsis: Upgrade of Edigraf to Ubuntu 18.04 |
| + | |
| + | RI Notes: In RI planning phase only. Project information can be found at: <nowiki>http://dvwiki.science.gc.ca/wiki/Edigraf_port_project</nowiki> |
| + | |- |
| + | |'''None''' |
| + | | |
| + | | |
| + | | |
| + | | |
| + | | |
| + | |- |
| + | | |
| + | | |
| + | | |
| + | | |
| + | | |
| + | | |
| + | |- |
| + | | |
| + | | |
| + | | |
| + | | |
| + | | |
| + | | |
| + | |} |