Difference between revisions of "NTTO test"
m |
m |
||
Line 1: | Line 1: | ||
− | '''<u><big> | + | '''<u><big>ATTENTION: THIS IS A TEST PAGE FOR NTTO GROUP. ALL RI CALENDARS DISPLAYED ARE OUT OF DATE AND ARE PRIMARILY USED FOR TESTING PURPOSES OF THIS SITE. RI SUMMARY IS ALSO PURELY FOR TEST PURPOSES UNTIL FURTHER NOTICE.</big></u>'''[[File:RI-Calendar-Webpart-2019-06-03.png|border|center|907x907px]] |
[[File:RI-Calendar-Webpart-2019-05-10.png|thumb|test]] | [[File:RI-Calendar-Webpart-2019-05-10.png|thumb|test]] | ||
{| class="wikitable" | {| class="wikitable" |
Revision as of 10:50, 9 July 2019
ATTENTION: THIS IS A TEST PAGE FOR NTTO GROUP. ALL RI CALENDARS DISPLAYED ARE OUT OF DATE AND ARE PRIMARILY USED FOR TESTING PURPOSES OF THIS SITE. RI SUMMARY IS ALSO PURELY FOR TEST PURPOSES UNTIL FURTHER NOTICE.
RI | Scope | Deployment Date | Milestone Dates | Testing Resources | Comments |
---|---|---|---|---|---|
24.1.1 | URP-IV (2.3.1) | June 18, 2019 | 1. Integration/UAT: now-June 17, 2019 | 1. NTTO/PSD | Synopsis: URP IV upgrade. Enhancements to IV to accommodate S-band radars. This is the 12.04 version. The 18.04 version will be deployed with IFWUU.
RI Notes: Testing in progress on RI testing IFW's. Here is a summary of the changes: • Animation improvements for products with different time increments – specifically for S-band radars (Mantis 20364, 19683) • Bug fix: CELL VIEW window launched from IV SCIT sometimes loads with no data. This can also result in IV loop lock. (Mantis 20510) |
24.2 | Aviation Changes | June 20, 2019 | Testing completed. | Synopsis: wxapps program changes...
http://msc-mantis.to.on.ec.gc.ca/mantis/view.php?id=20779 http://msc-mantis.to.on.ec.gc.ca/mantis/view.php?id=20776 RI Notes: Testing completed. We are ready to deploy. | |
24.X | URP 2.13.1 | July 23, 2019 | Package submission: June 21, 2019
1. Beta: now - June 20 2. Integration: June 24-28 3. UAT: July 2-22 |
1. URP dev team
2. NTTO 3. PSD |
Synopsis: Change details included in Section C of RFI: https://ecollab.ncr.int.ec.gc.ca/theme/165/RFI/CIC-2019-RFI014-URP-2_13.docx
RI notes: Radar data for temporary X-band radars will not be available in IV until later in summer. |
24.X | Upgrade wxapps servers to 18.04 | July 16-17, 2019 | 1. Test wxapps-beta servers: June 19-28, 2019
2. Test wxapps-stage servers: June 28-July 12, 2019 |
1. PSD: 2 (2d)
2. PSD: 2 (1d) |
Synopsis: Upgrade WxApps servers to Ubuntu 18.04.
RI Notes: 18.04 components have been submitted: Components-WxApps.xlsx. There has been some delay in building 18.04 wxapps-beta servers. |
24.X | Aviation Changes | August 15, 2019 | TBD | TBD | Synopsis: Aviation program changes.
RI Notes: NTTO are awaiting RFI submission. |
24.X | IFW Ubuntu Upgrade (IFWUU) | Sep 10-12, 2019 | 1. Creation of ops and non-ops testing IFW is each office: now-July 8, 2019
2. Live UAT on ops IFW: July 16 - Sep 9, 2019 |
1. NTTO and SSC
2. As many forecasters as possible |
Synopsis: Upgrade of IFW from Ubuntu12.04 to 18.04. Includes renaming of all IFW's according to new national SSC standard and 18.04 release of URP-IV (to accommodate 6 minute S-band data).
RI Notes: This project has restarted but there is a risk of delay. First priority is to setup KDE 18.04 test environments in all offices. |
25.0 | NinJo 3.4 (WPR1.5, Tsunami) + Scribe | September 24, 2019 | Scribe packages: June 19, 2019 (for Beta)
NinJo packages: July 10, 2019 (for Integration) Beta: June 20-Jul 9, 2019 Integration: Jul 16-Aug 16, 2019 UAT: Aug 26-Sep 9, 2019 |
1. FSII only
2. 1 (2d) 3. 1 (3h) |
Synopsis: NinJo 3.4 MSC config release (including WPR-O Release 1.5 and deployment of Tsunami alerts in MWAS) plus changes to Scribe.
RI Notes: PSD testing resources required for Integration and UAT. |
25.X | Edigraf Ubuntu Upgrade | September 2019 | TBD | TBD | Synopsis: Upgrade of Edigraf to Ubuntu 18.04
RI Notes: In RI planning phase only. Project information can be found at: http://dvwiki.science.gc.ca/wiki/Edigraf_port_project |
None | |||||
25.X | Aviation Changes | October 10, 2019 | TBD | TBD | Synopsis: Aviation program changes.
RI Notes: NTTO are awaiting RFI submission |
25.X | URP 2.13.2 | Oct 29, 2019 | Package submission: Sep 27, 2019
1. Beta: now - Sep 27 2. Integration: Oct 1 - 8 3. UAT: Oct 8 - 22 |
1. URP dev team
2. NTTO 3. PSD |
a. Removal of all decommissioned C and X-bands
b. Promotion of the remaining S-bands to Primary for SWP |
25.X | Aviation Changes | December 5, 2019 | TBD | TBD | Synopsis: Aviation program changes.
RI Notes: NTTO are awaiting RFI submission |
25.X | Upgrade NinJo servers to 18.04 | November 2019 | Synopsis: Upgrade NinJo servers to Ubuntu 18.04.
RI Notes: In planning phase only. | ||
25.X | Scribe | January, 2020 | Beta: TBD.
Integration: TBD. UAT: TBD. |
TBD | Synopsis: Intermediate RI for Scribe config changes:
- Realign NAVTEX areas - Configure Quebec meso-regions in Public Scribe RI Notes: Navtex realignment: The Canadian Coast Guard (CCG) has requested modifications to the FQCN3x/9x NAVTEX bulletins. |
25.X | Aviation Changes | January 30, 2020 | TBD | TBD | Synopsis: Aviation program changes.
RI Notes: NTTO are awaiting RFI submission. |
25.X | URP 2.14 | March 31, 2020 | Package submission: February 21, 2020
1. Integration: Feb 27-March 13, 2020 2. UAT: March 16-27, 2020 |
1. FSII only
2. 1 (3h) |
Synopsis: URP 2.14. Primary changes include:
• Dual pol particle classification & QPE products • Other algorithm improvements • 2020 radar configurations RI Notes: In planning phase. |