Difference between revisions of "Place du Portage III AWR Notices to tenants/occupants"
Jump to navigation
Jump to search
Layal.eshak (talk | contribs) |
Layal.eshak (talk | contribs) |
||
Line 5: | Line 5: | ||
<!--French--> | <!--French--> | ||
{| class="FCK__ShowTableBorders" style="border:white solid 1px; background-color:#551155" width="10%" align="center" | {| class="FCK__ShowTableBorders" style="border:white solid 1px; background-color:#551155" width="10%" align="center" | ||
− | | style="padding-right: 5px; padding-left: 5px; padding-bottom: 10px; padding-top: 10px; text-align: center;" | [[ | + | | style="padding-right: 5px; padding-left: 5px; padding-bottom: 10px; padding-top: 10px; text-align: center;" | [[Renouvellement_de_Portage_III_Avis_aux_occupants_du_bâtiment|<span style="color:#ffffff"> '''Français'''</span>]] |
|} <br> | |} <br> | ||
Revision as of 19:15, 21 April 2022
Français |
Project overview | Project phases and milestones | Objectives and benefits | Notices to building occupants | More information |
Notices to tenants/occupants
Tenants of PDP3 and adjacent buildings have been informed of construction work through operational notices issued by BGIS, with PSPC’s informal consent. Notices issued to date are provided below. This list will be updated regularly.
Title (link) | Release Date | Purpose |
---|---|---|
Construction hoarding activities | April 6, 2022 | The main objective of the construction hoarding activities is to create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project. |
Environmental Soil Study Characterization | April 5, 2022 | To help identify potential contaminants in the soil in and around the project area. Information gathered during this work will help describe the environmental quality of the soil. |
Tree Removal Activities | March 25, 2022 | To facilitate additional site logistics requirements for the Construction Manager (CM) to enable construction related activities in preparation of the PDP3 AWR Project and to update the landscape and riverfront greenbelt in connection to the complex. |
Construction hoarding activities (Interim space) | February 22, 2022 | To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project. |
Construction hoarding (CM site) | February 17, 2022 | To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project. |
Construction hoarding | February 11, 2022 | To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project. |
Tree removal activities (Woodland Area) | February 9, 2022 | To create an interim construction laydown area for the CM to enable construction related activities in preparation of the PDP3 AWR Project; and an opportunity to update the landscape and Riverfront Greenbelt connection to the complex. |