|'''[https://wiki.gccollab.ca/images/4/46/Asbestos_Abatement_Tower_A.F1.E%26F.pdf Tower Crane 2 (TC-2): Structural Steel Upgrades]'''
+
|'''[https://wiki.gccollab.ca/images/5/5e/CN38_Structural_Steel_Upgrades_in_Laurier-Tach%C3%A9_Parking_Garage.F.pdf Tower Crane 2 (TC-2): Structural Steel Upgrades]'''
 
|October 27, 2022
 
|October 27, 2022
 
   
 
   
 
|To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
 
|To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/4/46/Asbestos_Abatement_Tower_A.F1.E%26F.pdf Temporary Disruption of Domestic Water Supply On Emergency Basis]'''
+
|'''[https://wiki.gccollab.ca/images/7/77/CN-36_Domestic_Water_Service_Interruption_R3.pdf Temporary Disruption of Domestic Water Supply On Emergency Basis]'''
 
|October 21, 2022
 
|October 21, 2022
 
   
 
   