Changes

Jump to navigation Jump to search
Line 38: Line 38:  
   
 
   
 
|To facilitate the following renovations: installation of a new elevator pit; an interruption in the ventilation system; structural upgrades; and replacement of underground piping.
 
|To facilitate the following renovations: installation of a new elevator pit; an interruption in the ventilation system; structural upgrades; and replacement of underground piping.
|-
  −
|'''[https://wiki.gccollab.ca/images/2/2a/GOC479411_PDP3_AWR_Tower_B_Exterior_Hoarding.Final.pdf Hoarding Wall: Tower B Exterior]'''
  −
|July 29, 2022
  −
  −
|To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/d/d2/GOC479411-PDP_3_AWR-Place_de_Portage_IV_Bike_Storage.Final.pdf Relocation of the bicycle storage shelter at Tower C2 entrance hall at Level 02]'''
  −
|July 29, 2022
  −
  −
|To facilitate the additional site logistics required for the Construction Manager to install exterior hoarding in preparation for construction work.
   
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/1/13/1-_Tower_A_and_B_Delineation_Hoarding.pdf Tower A and B Delineation Hoarding]'''
 
|'''[https://wiki.gccollab.ca/images/1/13/1-_Tower_A_and_B_Delineation_Hoarding.pdf Tower A and B Delineation Hoarding]'''

Navigation menu

GCwiki