| Line 121: |
Line 121: |
| | | | | | |
| | |- | | |- |
| − | |Migration Complete for All Applications/Platforms | + | |Application Inventory |
| − | |2022-12-09 | + | |2021-03-31 |
| − | |2022-12-09 | + | |2022-03-31 |
| | | | | | |
| | + | | |
| | + | | |
| | + | | |
| | + | |- |
| | + | |Definition of Migration Criteria |
| | + | |2021-03-31 |
| | + | |2022-03-31 |
| | + | | |
| | + | | |
| | + | | |
| | + | | |
| | + | |- |
| | + | |Wave 0 Apps (15) |
| | + | |2021-03-31 |
| | + | |2022-03-31 |
| | + | | |
| | + | | |
| | + | | |
| | + | | |
| | + | |- |
| | + | |Update of TC Cloud/EDC Migration Strategy |
| | + | |2021-03-31 |
| | + | |2022-03-31 |
| | + | | |
| | + | || |
| | + | | |
| | + | |- |
| | + | |Seek Approval for Re-baseline of Project Schedule and Cost (Based on GoC Cloud Strategy Finalization) |
| | + | |2021-03-31 |
| | + | |2022-03-31 |
| | + | | |
| | + | || |
| | + | | |
| | + | |- |
| | + | |Wave 1 Apps (55) |
| | + | |2022-03-31 |
| | + | |2023-03-31 |
| | + | | |
| | + | || |
| | + | | |
| | + | |- |
| | + | |Wave 2 Apps (75) |
| | + | |2023-03-31 |
| | + | |2024-03-31 |
| | + | | |
| | + | || |
| | + | | |
| | + | |- |
| | + | |Wave 3 Apps (85) |
| | + | |2024-03-31 |
| | + | |2025-03-31 |
| | + | | |
| | + | || |
| | + | | |
| | + | |- |
| | + | |Wave 4 Apps (95) |
| | + | |2025-03-31 |
| | + | |2026-03-31 |
| | + | | |
| | + | || |
| | | | | | |
| | |- | | |- |