== Project Status ==
 
== Project Status ==
   −
This project will use where possible the Agile methodology, following the TC Project Management Office Framework 4 Gate model. TC Azure Cloud foundation build activities and planning for the migration of applications into the Cloud are on track. Overall the project is behind schedule due to the delay of secure network connectivity ("Cloud to Ground" connection) and/or authentication services (Active Directory - AD); this work is expected to be delivered by SSC. TC's Cloud Foundational Environment (Azure) has been granted "Authority to Operate" (ATO) (up to Protected-B) for applications not requiring secure network connectivity and/or authentication. In order to execute and to validate the migration process, a list of unclassified applications for migration to the Cloud has been created. Phase 3 of the project (define the migration process and migrate first set of applications) has started to migrate unclassified applications identified in Sprint #1. The presentation to GC-EARB for Application Modernization and Cloud Enablement has been approved by TBS. The resulting MOU for funding has been approved and signed by TBS and TC.    
+
This project will use where possible the Agile methodology, following the TC Project Management Office Framework 4 Gate model. TC Azure Cloud foundation build activities and planning for the migration of applications into the Cloud are on track. Overall the project is behind schedule due to the delay of secure network connectivity (Cloud to Ground SCED connection) and/or authentication services (Active Directory - AD); this work is expected to be delivered by SSC. TC's Cloud Foundational Environment (Azure) has been granted "Authority to Operate" (ATO) (up to Protected-B) for applications not requiring secure network connectivity and/or authentication. In order to execute and to validate the migration process, a list of unclassified applications for migration to the Cloud has been created. Phase 3 of the project (define the migration process and migrate first set of applications) has started to migrate unclassified applications identified in Sprint #1. The presentation to GC-EARB for Application Modernization and Cloud Enablement has been approved by TBS. The resulting MOU for funding has been approved and signed by TBS and TC.    
    
{| class="wikitable mw-collapsible"
 
{| class="wikitable mw-collapsible"
Line 41: Line 41:  
|Complete: Initial research  for establishing a Disaster Recovery Program for TC
 
|Complete: Initial research  for establishing a Disaster Recovery Program for TC
 
|-
 
|-
|Gate 0 Phase 1: Discovery and Initial Cloud Foundation build
+
|Gate 0 Phase 1: Discovery and Initial Cloud Foundation
 
|2019-04-29
 
|2019-04-29
 
|2019-04-01
 
|2019-04-01
Line 57: Line 57:  
|2020-04-30
 
|2020-04-30
 
|
 
|
|While TC had requested an  initial target date of July, 2018, per the SCED project, TC is scheduled to have the connectivity in April, 2020. Until the connectivity is available, TC cannot put into production any applications into the Cloud that require connectivity to an Enterprise data centre
+
|TC had requested an  initial target date of July 2018 per the SCED project but is not scheduled to have secure connectivity until March 2021. Until the SCED is available, TC cannot put into production any Cloud applications that require connectivity to an Enterprise data centre.
 
|-
 
|-
 
|Cloud  Foundation Build  
 
|Cloud  Foundation Build  
Line 63: Line 63:  
|2019-10-18
 
|2019-10-18
 
|2019-10-18
 
|2019-10-18
|Complete (except for Cloud to Ground SCED secure infrastructure): This is the Cloud Working environment for TC applications
+
|Complete (except for Cloud to Ground SCED secure connectivity). This is the Cloud Working environment for TC applications.
 
|-
 
|-
 
|First  Sprint of migrating applications to the Cloud
 
|First  Sprint of migrating applications to the Cloud