Line 145: |
Line 145: |
| === Issues: === | | === Issues: === |
| * Missing secure network connectivity "Cloud to Ground". | | * Missing secure network connectivity "Cloud to Ground". |
− | '''Resolution Plan''': Re-order activities to migrate workloads that have minimum dependency on Network requirements first. Working to ensure TC is on the next wave of SCED planning. | + | '''Resolution Plan''': Re-order activities to migrate workloads that have minimum dependency on Network requirements first. Working to ensure TC is on the next wave of SCED planning. |
− | * The contracts for Protected B Cloud services were available August, 2019, however, the required connectivity from "Cloud to ground" and associated services have not been delivered. This delay is impacting Workload Migration activities for Protected-B workloads.
| |
− | '''Resolution Plan''': Re-order activities to migrate unclassified workloads first; work to expedite the implementation of a secure tunnel and the required foundational services.
| |
| | | |
| == Guidance and Documentation == | | == Guidance and Documentation == |
Line 199: |
Line 197: |
| |} | | |} |
| == Application Workload Migration via Agile Sprints == | | == Application Workload Migration via Agile Sprints == |
− | Placeholder to identify applications for upcoming Workload Migration of Applications via Agile Sprints
| + | Current phase activity is to define the migration process and migrate first set of applications. The phase has 4 sprints of 4 weeks each (refinement of application choice and schedule can occur as per an agile process). |
| + | {| class="wikitable" |
| + | |Phase # |
| + | |Sprint # |
| + | |'''Acronym''' |
| + | |'''Application Name''' |
| + | |- |
| + | |1 |
| + | |1 |
| + | |'''CIRS''' |
| + | |'''Collision Investigation Reporting System''' |
| + | |- |
| + | |1 |
| + | |1 |
| + | |'''CUMULUS''' |
| + | |'''Canto Cumulus''' |
| + | |- |
| + | |1 |
| + | |1 |
| + | |'''LDPS''' |
| + | |'''Lobby Display Panel''' |
| + | |- |
| + | |1 |
| + | |3 |
| + | |'''LOGCAS''' |
| + | |'''Lenel OnGuard Card Access System''' |
| + | |- |
| + | |1 |
| + | |2 |
| + | |'''MAPINFO''' |
| + | |'''MapInfo Version 8.0''' |
| + | |- |
| + | |1 |
| + | |3 |
| + | |'''MEDA''' |
| + | |'''Maintenance Error Decision Aid''' |
| + | |- |
| + | |1 |
| + | |2 |
| + | |'''MTS''' |
| + | |'''MultiTrans 5.7''' |
| + | |- |
| + | |1 |
| + | |4 |
| + | |'''NWAR-E''' |
| + | |'''Navigable Waters Act Renewal (External)''' |
| + | |- |
| + | |1 |
| + | |3 |
| + | |'''PCDB''' |
| + | |'''PCDB Manufacturer Portal''' |
| + | |- |
| + | |1 |
| + | |2 |
| + | |'''RLD''' |
| + | |'''Regional Labour Distribution''' |
| + | |- |
| + | |1 |
| + | |2 |
| + | |'''RSIG''' |
| + | |'''Rail Safety Integrated Gateway''' |
| + | |- |
| + | |1 |
| + | |1 |
| + | |'''SAP-BI''' |
| + | |'''SAP BusinessObjects Enterprise''' |
| + | |- |
| + | |1 |
| + | |1 |
| + | |'''SN''' |
| + | |'''Serial Numbers''' |
| + | |- |
| + | |1 |
| + | |1 |
| + | |'''SNAGS''' |
| + | |'''SNAGS''' |
| + | |- |
| + | |1 |
| + | |3 |
| + | |'''TeamMate Suite''' |
| + | |'''TeamMate Suite''' |
| + | |- |
| + | |1 |
| + | |3 |
| + | |'''TRACE-ME''' |
| + | |'''TRACE ME Software''' |
| + | |- |
| + | |1 |
| + | |2 |
| + | |'''WTS/MSPI''' |
| + | |'''Web Timesheet with Microsoft Project Integration''' |
| + | |} |
| | | |
| == Activities and Timelines for TC's Cloud Adoption Strategy == | | == Activities and Timelines for TC's Cloud Adoption Strategy == |