Line 34: Line 34:  
!'''Purpose'''
 
!'''Purpose'''
 
|-
 
|-
|'''[ https://wiki.gccollab.ca/images/f/f6/CN29.2_Tower_Crane_Installation_Laurier-Tach%C3%A9_Parking_Garage.F2.pdf Tower Crane Installation in Laurier-Taché Parking Garage (UPDATED)]'''
+
|'''[https://wiki.gccollab.ca/images/7/75/CN65_-_Fermeture_De_L%27escalier_De_Secours_Ext%C3%A9rieur_-_Closure_Of_Exterior_Emergency_Exit_Staircase.pdf Temporary Closure of Exterior Emergency Staircase]'''
|January 19, 2023
+
|March 16, 2023
 +
 +
|To allow for investigations and repairs to the compromised structural slab in Tower A (L03).
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/0/02/CN60.2_-_Installation_D%27Une_Grue_%C3%80_Tour_%28G-2%29_-_Notice_of_Tower_Crane_%28TC-2%29_Installation.pdf Notice of Tower Crane (TC-2) Installation (UPDATED)]'''
 +
|March 13, 2023
 +
 +
|To install a tower crane (TC-2) within the construction zone in front of Place du Portage III Tower B on Laurier Street.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/e/e1/CN63_Tour_B1_et_A2_D%C3%A9couplage_des_Syst%C3%A8mes_m%C3%A9caniques_-_Decoupling_of_Towers_B1_A2_Mechanical_Systems.F.pdf Tower B1 & A2: Decoupling of Mechanical Systems]'''
 +
|March 13, 2023
 +
 +
|To separate the mechanical systems in Tower A2 from Tower B1.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/1/1f/CN66_-_Remplacement_des_Composants_de_l%27Appareillage_d%27Alimentation_-_Switchgear_maintenance_for_Tower_C.pdf High Voltage Switchgear Component Replacement Feeding Tower C]'''
 +
|March 13, 2023
 +
 +
|To perform needed maintenance to the High voltage Switchgear supplying power to Tower C.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/5/57/CN67.2_-_D%C3%A9placement_de_la_salle_des_batteries_et_%C3%A9quipement_associ%C3%A9s_-_Re-Location_of_the_Switchgear_battery_room_and_associated_equipment_.pdf Re-location of Switchgear Battery Room and Associated Equipment (UPDATED)]'''
 +
|March 10, 2023
 +
 +
|To re-locate the batteries and associated equipment that support the Switchgear which provides power complex wide.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/5/5c/CN62_D%C3%A9limitation_et_palissade_de_construction_tour_B1_-_Construction_Hoarding_Tower_B1_L5.pdf Tower B1: Delineation and Hoarding Wall (L5)]'''
 +
|February 24, 2023
 +
 +
|To outline and separate the occupied space from the demolition and abatement activities.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/7/7c/CN64_D%C3%A9molition_et_Construction_Tour_B1_N5_-_Demolition_Tower_B1_L5.pdf Tower B1: Demolition and Construction Activities (L5)]'''
 +
|February 24, 2023
 +
 +
|To complete Place du Portage III Asset and Workplace Renewal Project scheduled renovations.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/2/29/CN61_Orientation_de_Site_Code_QR_Install%C3%A9_-_Site_Wayfinding_QR_Code_Installed.pdf Site Wayfinding QR Code]'''
 +
|February 16, 2023
 +
 +
|To provide a quick and paperless link to wayfinding on Portage III and Portage IV's site as part of the Place du Portage III AWR Project.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/c/c6/CN54.2_Tour_D_et_E_Delimitation_et_Palissade_de_construction_-_Tower_D_and_E_Delineation_Hoarding_%28002%29.pdf Towers D & E: Delineation and Hoarding Wall (UDPATED)]'''
 +
|February 15, 2023
 +
 +
|To outline and separate the occupied space from the demolition and abatement activities.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/0/02/CN58.1_Electrical_Shutdown_in_Sub-Sector_Garage_mod_R1.pdf Electrical Shutdown in Laurier-Taché Parking Garage (Maisonneuve Sector) (UPDATED)]'''
 +
|February 8, 2023
 +
 +
|To proceed with scheduled Tower C electrical maintenance.  
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/d/d7/CN57._3_Tower_A_Storm_and_Sanitary_Pipe_Replacement.F2_.pdf Tower A: Storm and Sanitary Pipe Installation (UPDATED)]'''
 +
|February 3, 2023
 +
 +
|To demolish the existing pipe and reinstall a new underground sanitary and storm one in L03 (A0314) in Tower A.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/e/eb/CN38.2_Structural_Steel_Upgrades_in_Laurier-Tach%C3%A9_Parking_Garage.F2.pdf Tower Crane 2 (TC-2): Structural Steel Upgrades (UPDATED)]'''
 +
|January 27, 2023
 +
 +
|To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/9/91/CN17.1_Mission_Critical_Spaces_Tower_A-F1.pdf Mission Critical Spaces (L15)]'''
 +
|January 27, 2023
 +
 +
|To complete A1 and A2 Towers construction fit up, to accommodate B1 Tower tenants.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/c/cf/CN59_Tower_B3_Delineation_and_Hoarding_Wall.F2.pdf Tower B3: Delineation and Hoarding Wall (L0)]'''
 +
|January 20, 2023
 
   
 
   
|To prepare the site for the construction and installation of the tower crane (TC-2).  
+
|To outline and separate the occupied space from the demolition and abatement activities.  
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/3/3a/CN54.1_Tower_D_and_E_Delineation_Hoarding.F2.pdf Towers D & E: Delineation and Hoarding Wall (UDPATED)]'''
+
|'''[https://wiki.gccollab.ca/images/8/8f/CN50.1_Construction_Hoarding_Tower_B3_L01_L02F1.pdf Tower B3: Delineation and Hoarding Wall (L01 & L02)]'''
|January 18, 2022
+
|January 19, 2023
 
   
 
   
 
|To outline and separate the occupied space from the demolition and abatement activities.  
 
|To outline and separate the occupied space from the demolition and abatement activities.  
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/5/5f/CN53.1_Construction_Hoarding_Tower_B1_L4_L8.F1.pdf Tower B1: Delineation and Hoarding Wall (UPDATED)]'''
+
|'''[https://wiki.gccollab.ca/images/f/f6/CN29.2_Tower_Crane_Installation_Laurier-Tach%C3%A9_Parking_Garage.F2.pdf Tower Crane Installation in Laurier-Taché Parking Garage (UPDATED)]'''
|January 17, 2022
+
|January 19, 2023
 
   
 
   
|To outline and separate the occupied space from the demolition and abatement activities.
+
|To prepare the site for the construction and installation of the tower crane (TC-2).  
 
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/7/73/CN55_Tower_E_Construction_of_Partition_Wall.F1.V2.pdf Tower E: Construction of Partition Wall]'''
 
|'''[https://wiki.gccollab.ca/images/7/73/CN55_Tower_E_Construction_of_Partition_Wall.F1.V2.pdf Tower E: Construction of Partition Wall]'''
Line 54: Line 119:  
|To outline and separate the occupied space from the bulk of demolition and abatement activities while the Security Operations Centre remains in place (02B2-101).  
 
|To outline and separate the occupied space from the bulk of demolition and abatement activities while the Security Operations Centre remains in place (02B2-101).  
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/f/f5/CN57_Tower_A_Storm_and_Sanitary_Pipe_Replacement.F.pdf Tower A: Storm and Sanitary Pipe Installation]'''
+
|'''[https://wiki.gccollab.ca/images/a/aa/CN_56_Temporary_Disruption_to_Garage_Door_Openers.Canceled1.pdf Temporary Disruption to the Laurier-Taché Parking Garage Door Operators (CANCELED)]'''
|January 4, 2023
  −
  −
|To demolish the existing pipe and reinstall a new underground sanitary and storm one in L03 (A0314) in Tower A.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/d/d3/CN56_Temporary_Disruption_to_Garage_Door_Openers.F1_%282%29.pdf Temporary Disruption to the Laurier-Taché Parking Garage Door Operators]'''
   
|January 3, 2023
 
|January 3, 2023
 
   
 
   
Line 89: Line 149:  
   
 
   
 
|To assist in the removal of the exterior envelope of Towwers C1/C2.
 
|To assist in the removal of the exterior envelope of Towwers C1/C2.
|-
  −
|'''[https://wiki.gccollab.ca/images/5/52/CN38.1_Structural_Steel_Upgrades_in_Laurier-Tach%C3%A9_Parking_Garage.F.pdf Tower Crane 2 (TC-2): Structural Steel Upgrades (UPDATED)]'''
  −
|November 25, 2022
  −
  −
|To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
   
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/c/c0/CN44_Temporary_Shutdown_of_Primary_Chilled_Water_Loop.F.Nov25.pdf Temporary Shutdown of Primary Chilled Water Loop (UPDATED)]'''
 
|'''[https://wiki.gccollab.ca/images/c/c0/CN44_Temporary_Shutdown_of_Primary_Chilled_Water_Loop.F.Nov25.pdf Temporary Shutdown of Primary Chilled Water Loop (UPDATED)]'''
Line 119: Line 174:  
   
 
   
 
|To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
 
|To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
|-
  −
|'''[https://wiki.gccollab.ca/images/2/2b/CN35_fermeture_temporaire_acc%C3%A8s_au_quai_de_chargement_PDC-Temporary_Closure_of_Access_Route_to_Place_du_Centre_Loading_Dock02N.2022.pdf Place du Centre: Temporary Closure of Access Route to Loading Dock]'''
  −
|November 4, 2022
  −
  −
|To allow space to park a 90-Ton crane and assist with the installation of overhead protection.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/a/aa/CN-40_Tower_B1_L3_Asbestos_Abatement..F.pdf Asbestos Abatement in Tower B1 (L3)]'''
  −
|October 31, 2022
  −
  −
|To prepare the site for a new set of doors and to allow a new passage to the freight elevator in Tower A.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/d/d0/CN-39_Construction_Hoarding_PDPIV_Mechanical_Room.Final.pdf Delineation and Hoarding Wall in Mechanical Room]'''
  −
|October 28, 2022
  −
  −
|To delineate the construction space required to install the shear wall for PDP III Tower C as part of the PDP3 AWR Project.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/7/77/CN-36_Domestic_Water_Service_Interruption_R3.pdf Temporary Disruption of Domestic Water Supply On Emergency Basis]'''
  −
|October 21, 2022
  −
  −
|The main objective of the domestic water shutdown is due to concerns over the integrity of the pipe, and is required to allow for the reinforcement of the primary city water feed to Tower C ahead of excavation. This request is based on the emergency basis to replace Isolation valve of the fire suppression system.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/4/46/Asbestos_Abatement_Tower_A.F1.E%26F.pdf Tower A: Asbestos Abatement in Swing Spaces for Critical Tenants' Operations (L15)]'''
  −
|October 19, 2022
  −
  −
|To prepare the interim space for Tower B occupants.
   
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/1/17/Installation_of_Tower_Crane_in_Construction_Area.f.pdf Erection of Tower Crane (TC-1) in the construction area between PDP3 and PDP4 (Woodlands area)]'''
 
|'''[https://wiki.gccollab.ca/images/1/17/Installation_of_Tower_Crane_in_Construction_Area.f.pdf Erection of Tower Crane (TC-1) in the construction area between PDP3 and PDP4 (Woodlands area)]'''
Line 149: Line 179:  
   
 
   
 
|The erection of the tower crane (TC-1) is one of the PDP3 AWR Project milestones as it visually symbolizes the beginning of the demolition activities.
 
|The erection of the tower crane (TC-1) is one of the PDP3 AWR Project milestones as it visually symbolizes the beginning of the demolition activities.
|-
  −
|'''[https://wiki.gccollab.ca/images/4/44/Tower_B1_Delineation_HoardingF.Bgis.pdf Towers A & B: Delineation and Hoarding Wall (L1, L2 and L3)]'''
  −
|September 26, 2022
  −
  −
|To outline and separate the occupied space in Tower A2 from the construction activities in Tower B1.
   
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/3/34/GOC479411_AWR_PDP3_-_Bicycle_Shelter_New_Location.Final.pdf Bicycle Enclosure Relocation]'''
 
|'''[https://wiki.gccollab.ca/images/3/34/GOC479411_AWR_PDP3_-_Bicycle_Shelter_New_Location.Final.pdf Bicycle Enclosure Relocation]'''
Line 169: Line 194:  
   
 
   
 
|How to circulate between PDP4 and the A/B/E towers of PDP3 (interior).
 
|How to circulate between PDP4 and the A/B/E towers of PDP3 (interior).
|-
  −
|'''[https://wiki.gccollab.ca/images/0/05/CN-23_Tree_Removal_at_Courcelette_and_Laurier_F.pdf Removal of Trees and Shrubs]'''
  −
|August 22, 2022
  −
  −
|To prepare the area for the upcoming construction of the curtain wall mockup.
   
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/0/02/Laurier_Sidewalk_Closure_%28CN-24%29.pdf Sidewalk Closure: Laurier Street]'''
 
|'''[https://wiki.gccollab.ca/images/0/02/Laurier_Sidewalk_Closure_%28CN-24%29.pdf Sidewalk Closure: Laurier Street]'''
Line 184: Line 204:  
   
 
   
 
|To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
 
|To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
|-
  −
|'''[https://wiki.gccollab.ca/images/a/ad/PDP_IV_Sign_Reinstatement_%28CN-14%29.F.pdf PDP IV: Sign replacement]'''
  −
|August 15, 2022
  −
  −
|To install the new PDP IV sign onto the exterior corner of the building, next to the Woodlands Area.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/d/d1/GOC479411-PDP_3_AWR-Critical_Spaces.F.pdf Mission Critical Spaces]'''
  −
|August 2, 2022
  −
  −
|To complete A1 and A2 Towers construction fit up, to accommodate B1 Tower tenants.
   
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/d/dd/GOC479411_PDP_3_AWR_-_PDP_IV_Wayfinding.pdf Place du Portage IV: Wayfinding]'''
 
|'''[https://wiki.gccollab.ca/images/d/dd/GOC479411_PDP_3_AWR_-_PDP_IV_Wayfinding.pdf Place du Portage IV: Wayfinding]'''
Line 199: Line 209:  
   
 
   
 
|To facilitate the construction renovations, including the Tower C Curtainwall Upgrades; Tower C Interior Upgrades; and Structural Upgrades for the Place du Portage AWR Project.
 
|To facilitate the construction renovations, including the Tower C Curtainwall Upgrades; Tower C Interior Upgrades; and Structural Upgrades for the Place du Portage AWR Project.
|-
  −
|'''[https://wiki.gccollab.ca/images/1/1d/GOC479411-PDP_3_AWR-Tower_A_and_B_Delineation_Hoarding.F.pdf Towers A & B: Delineation and Hoarding Wall]'''
  −
|August 2, 2022
  −
  −
|To outline and separate the occupied space in Tower A2 from the construction activities in Tower B1.
   
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/7/7c/Laurier-Tache_Parking_Garage_Closure-Maisonneuve.Aug2_FINAL.pdf Temporary Partial Closure: Laurier-Taché Parking Garage]'''
 
|'''[https://wiki.gccollab.ca/images/7/7c/Laurier-Tache_Parking_Garage_Closure-Maisonneuve.Aug2_FINAL.pdf Temporary Partial Closure: Laurier-Taché Parking Garage]'''
Line 214: Line 219:  
   
 
   
 
|To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
 
|To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
|-
  −
|'''[https://wiki.gccollab.ca/images/1/13/1-_Tower_A_and_B_Delineation_Hoarding.pdf Tower A and B Delineation Hoarding]'''
  −
|July 14, 2022
  −
  −
|Outline and separate the occupied space in Tower A2 from the construction activities in Tower B1.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/c/c5/2-Interim_Mailroom_Demolition_and_Abatement.pdf Interim Mailroom Demolition and Abatement]'''
  −
|July 14, 2022
  −
  −
|See notice
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/3/3f/GOC479411-_PDP_3_AWR-_Construction_de_la_salle_de_courrier_provisoire.Bgis.pdf Interim Mailroom Construction]'''
  −
|June 20, 2022
  −
  −
|See notice.
   
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/6/61/GOC479411-_PDP_3_AWR-_CM-_Avis_-_Maisonneuve.pdf Sidewalk and Lane Closure on Maisonneuve Boulevard]'''
 
|'''[https://wiki.gccollab.ca/images/6/61/GOC479411-_PDP_3_AWR-_CM-_Avis_-_Maisonneuve.pdf Sidewalk and Lane Closure on Maisonneuve Boulevard]'''
Line 234: Line 224:  
   
 
   
 
|To facilitate the additional site logistics required for the CM and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
 
|To facilitate the additional site logistics required for the CM and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
|-
  −
|'''[https://wiki.gccollab.ca/images/1/13/GOC479411-PDP_3_AWR-_CM-Tower_C_North_Couryard_Construction_Hoarding_C0_Communications_Notice.Final.pdf Construction Hoarding: Tower C - North Courtyard]'''
  −
|May 24, 2022
  −
  −
|To facilitate the additional site logistics required for the Construction Manager and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/5/5c/GOC479411-_PDP_3_AWR-_CM-Tower_B_Construction_Hoarding_Communications_Notice.Final.pdf Construction Hoarding: Tower B - Exterior]'''
  −
|May 24, 2022
  −
  −
|To facilitate the additional site logistics required for the Construction Manager and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/d/d7/1-_Construction_hoarding_activities.pdf Construction hoarding activities]'''
  −
|April 6, 2022
  −
  −
|The main objective of the construction hoarding activities is to create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/2/2c/2-Environmental_Soil_Study_Characterization.pdf Environmental Soil Study Characterization]'''
  −
|April 5, 2022
  −
  −
|To help identify potential contaminants in the soil in and around the project area. Information gathered during this work will help describe the environmental quality of the soil.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/5/50/3-_Tree_Removal_Activities.pdf Tree Removal Activities]'''
  −
|March 25, 2022
  −
  −
|To facilitate additional site logistics requirements for the Construction Manager (CM) to enable construction related activities in preparation of the PDP3 AWR Project and to update the landscape and riverfront greenbelt in connection to the complex.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/6/63/4-_Construction_hoarding_activities_%28Interim_space%29.pdf Construction hoarding activities (Interim space)]'''
  −
|February 22, 2022
  −
  −
|To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
  −
|-
  −
  −
|'''[https://wiki.gccollab.ca/images/5/5d/5-_Construction_hoarding_%28CM_site%29.pdf Construction hoarding (CM site)]'''
  −
|February 17, 2022
  −
  −
|To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/8/80/6-_Construction_hoarding.pdf Construction hoarding]'''
  −
|February 11, 2022
  −
  −
|To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
  −
|-
  −
|'''[https://wiki.gccollab.ca/images/7/76/7-_Tree_removal_activities_%28Woodland_Area%29.pdf Tree removal activities (Woodland Area)]'''
  −
|February 9, 2022
  −
  −
|To create an interim construction laydown area for the CM to enable construction related activities in preparation of the PDP3 AWR Project; and an opportunity to update the landscape and Riverfront Greenbelt connection to the complex.
   
|}
 
|}
 
<br>
 
<br>
 