Difference between revisions of "Place du Portage III AWR Notices to tenants/occupants"

From wiki
Jump to navigation Jump to search
 
(56 intermediate revisions by the same user not shown)
Line 1: Line 1:
<!--765e-->
+
'''<big>IMPORTANT: Please note that this site has been replaced by the new [https://www.gcpedia.gc.ca/wiki/PDP3AWR_Home PDP3 AWR Project Portal on GCpedia]; no further updates will be made.</big>'''<!--765e-->
 
[[Image:PDP3_Welcome_Page1.jpg|center|link=]]
 
[[Image:PDP3_Welcome_Page1.jpg|center|link=]]
 
<br>
 
<br>
Line 34: Line 34:
 
!'''Purpose'''
 
!'''Purpose'''
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/8/81/CN29.1_Tower_Crane_Installation-Laurier-Tach%C3%A9ParkingGarage.F.pdf Tower Crane Installation in Laurier-Taché Parking Garage]'''
+
|'''[https://wiki.gccollab.ca/images/7/75/CN65_-_Fermeture_De_L%27escalier_De_Secours_Ext%C3%A9rieur_-_Closure_Of_Exterior_Emergency_Exit_Staircase.pdf Temporary Closure of Exterior Emergency Staircase]'''
|November 25, 2022
+
|March 16, 2023
 
   
 
   
|To prepare the site for the construction and installation of the tower crane (TC-2).  
+
|To allow for investigations and repairs to the compromised structural slab in Tower A (L03).
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/c/c0/CN44_Temporary_Shutdown_of_Primary_Chilled_Water_Loop.F.Nov25.pdf Temporary Shutdown of Primary Chilled Water Loop (UPDATED)]'''
+
|'''[https://wiki.gccollab.ca/images/0/02/CN60.2_-_Installation_D%27Une_Grue_%C3%80_Tour_%28G-2%29_-_Notice_of_Tower_Crane_%28TC-2%29_Installation.pdf Notice of Tower Crane (TC-2) Installation (UPDATED)]'''
|November 25, 2022
+
|March 13, 2023
 
   
 
   
|To directly reconnect critical mechanical equipment (V-30, V-72 and V-74) to the primary chilled water loop to accommodate the demolition of the pumps and heat exchangers in Tower C Level 02. Space in the mechanical room is required for construction of the concrete shear wall and associated re-shoring.
+
|To install a tower crane (TC-2) within the construction zone in front of Place du Portage III Tower B on Laurier Street.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/e/ec/CN49_Removal_of_Emergency_Generator_Tower_C.Bgis.pdf Tower C: Emergency Generator Removal]'''
+
|'''[https://wiki.gccollab.ca/images/e/e1/CN63_Tour_B1_et_A2_D%C3%A9couplage_des_Syst%C3%A8mes_m%C3%A9caniques_-_Decoupling_of_Towers_B1_A2_Mechanical_Systems.F.pdf Tower B1 & A2: Decoupling of Mechanical Systems]'''
|November 18, 2022
+
|March 13, 2023
 
   
 
   
|To disconnect the Tower C generator and then reconnect its emergency load to the generator control panel in Tower B to ensure backup electricity in the event of an electrical power outage.
+
|To separate the mechanical systems in Tower A2 from Tower B1.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/d/d5/CN41_Construction_Hoarding-Tower_B1-L0.F.Nov17docx.pdf Tower B1 - Level 0: Construction Hoarding]'''
+
|'''[https://wiki.gccollab.ca/images/1/1f/CN66_-_Remplacement_des_Composants_de_l%27Appareillage_d%27Alimentation_-_Switchgear_maintenance_for_Tower_C.pdf High Voltage Switchgear Component Replacement Feeding Tower C]'''
|November 17, 2022
+
|March 13, 2023
 
   
 
   
|To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
+
|To perform needed maintenance to the High voltage Switchgear supplying power to Tower C.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/7/73/CN46_Demolition_Tower_B1_and_B3_%28L1_L2_L3%29F.Nov17.pdf Towers B1 & B3: Demolition and Construction Activities (L1, L2 & L3)]'''
+
|'''[https://wiki.gccollab.ca/images/5/57/CN67.2_-_D%C3%A9placement_de_la_salle_des_batteries_et_%C3%A9quipement_associ%C3%A9s_-_Re-Location_of_the_Switchgear_battery_room_and_associated_equipment_.pdf Re-location of Switchgear Battery Room and Associated Equipment (UPDATED)]'''
|November 17, 2022
+
|March 10, 2023
 
   
 
   
|To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
+
|To re-locate the batteries and associated equipment that support the Switchgear which provides power complex wide.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/8/84/CN45_Demolition_Tower_B1_and_B3_%28L6-L12%29.F.Nov17_%28002%29.pdf Towers B1 & B3: Demolition and Construction Activities (L6 to L12)]'''
+
|'''[https://wiki.gccollab.ca/images/5/5c/CN62_D%C3%A9limitation_et_palissade_de_construction_tour_B1_-_Construction_Hoarding_Tower_B1_L5.pdf Tower B1: Delineation and Hoarding Wall (L5)]'''
|November 17, 2022
+
|February 24, 2023
 
   
 
   
|To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
+
|To outline and separate the occupied space from the demolition and abatement activities.  
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/3/3f/CN27.1_Tower_B_Exterior_Civil_Works.Final.Nov17.pdf Tower B: Exterior Demolition]'''
+
|'''[https://wiki.gccollab.ca/images/7/7c/CN64_D%C3%A9molition_et_Construction_Tour_B1_N5_-_Demolition_Tower_B1_L5.pdf Tower B1: Demolition and Construction Activities (L5)]'''
|November 17, 2022
+
|February 24, 2023
 
   
 
   
|To install temporary new stairs to allow emergency access and egress during construction activities and demolish existing stairs.
+
|To complete Place du Portage III Asset and Workplace Renewal Project scheduled renovations.  
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/9/93/CN48_Construction_of_Safety_Orientation_Room.final.pdf Construction of Safety Orientation Room]'''
+
|'''[https://wiki.gccollab.ca/images/2/29/CN61_Orientation_de_Site_Code_QR_Install%C3%A9_-_Site_Wayfinding_QR_Code_Installed.pdf Site Wayfinding QR Code]'''
|November 14, 2022
+
|February 16, 2023
 
   
 
   
|To create an orientation room outside of the construction zone for the purpose of performing heath and safety orientations as part of the Place du Portage III AWR Project.
+
|To provide a quick and paperless link to wayfinding on Portage III and Portage IV's site as part of the Place du Portage III AWR Project.  
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/2/2b/CN35_fermeture_temporaire_acc%C3%A8s_au_quai_de_chargement_PDC-Temporary_Closure_of_Access_Route_to_Place_du_Centre_Loading_Dock02N.2022.pdf Place du Centre: Temporary Closure of Access Route to Loading Dock]'''
+
|'''[https://wiki.gccollab.ca/images/c/c6/CN54.2_Tour_D_et_E_Delimitation_et_Palissade_de_construction_-_Tower_D_and_E_Delineation_Hoarding_%28002%29.pdf Towers D & E: Delineation and Hoarding Wall (UDPATED)]'''
|November 4, 2022
+
|February 15, 2023
 
   
 
   
|To allow space to park a 90-Ton crane and assist with the installation of overhead protection.
+
|To outline and separate the occupied space from the demolition and abatement activities.  
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/a/aa/CN-40_Tower_B1_L3_Asbestos_Abatement..F.pdf Asbestos Abatement in Tower B1 (L3)]'''
+
|'''[https://wiki.gccollab.ca/images/0/02/CN58.1_Electrical_Shutdown_in_Sub-Sector_Garage_mod_R1.pdf Electrical Shutdown in Laurier-Taché Parking Garage (Maisonneuve Sector) (UPDATED)]'''
|October 31, 2022
+
|February 8, 2023
 
   
 
   
|To prepare the site for a new set of doors and to allow a new passage to the freight elevator in Tower A.
+
|To proceed with scheduled Tower C electrical maintenance.  
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/d/d0/CN-39_Construction_Hoarding_PDPIV_Mechanical_Room.Final.pdf Delineation and Hoarding Wall in Mechanical Room]'''
+
|'''[https://wiki.gccollab.ca/images/d/d7/CN57._3_Tower_A_Storm_and_Sanitary_Pipe_Replacement.F2_.pdf Tower A: Storm and Sanitary Pipe Installation (UPDATED)]'''
|October 28, 2022
+
|February 3, 2023
 
   
 
   
|To delineate the construction space required to install the shear wall for PDP III Tower C as part of the PDP3 AWR Project.
+
|To demolish the existing pipe and reinstall a new underground sanitary and storm one in L03 (A0314) in Tower A.  
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/5/5e/CN38_Structural_Steel_Upgrades_in_Laurier-Tach%C3%A9_Parking_Garage.F.pdf Tower Crane 2 (TC-2): Structural Steel Upgrades]'''
+
|'''[https://wiki.gccollab.ca/images/e/eb/CN38.2_Structural_Steel_Upgrades_in_Laurier-Tach%C3%A9_Parking_Garage.F2.pdf Tower Crane 2 (TC-2): Structural Steel Upgrades (UPDATED)]'''
|October 27, 2022
+
|January 27, 2023
 
   
 
   
 
|To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
 
|To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/7/77/CN-36_Domestic_Water_Service_Interruption_R3.pdf Temporary Disruption of Domestic Water Supply On Emergency Basis]'''
+
|'''[https://wiki.gccollab.ca/images/9/91/CN17.1_Mission_Critical_Spaces_Tower_A-F1.pdf Mission Critical Spaces (L15)]'''
|October 21, 2022
+
|January 27, 2023
 
   
 
   
|The main objective of the domestic water shutdown is due to concerns over the integrity of the pipe, and is required to allow for the reinforcement of the primary city water feed to Tower C ahead of excavation. This request is based on the emergency basis to replace Isolation valve of the fire suppression system.  
+
|To complete A1 and A2 Towers construction fit up, to accommodate B1 Tower tenants.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/4/46/Asbestos_Abatement_Tower_A.F1.E%26F.pdf Tower A: Asbestos Abatement in Swing Spaces for Critical Tenants' Operations (L15)]'''
+
|'''[https://wiki.gccollab.ca/images/c/cf/CN59_Tower_B3_Delineation_and_Hoarding_Wall.F2.pdf Tower B3: Delineation and Hoarding Wall (L0)]'''
|October 19, 2022
+
|January 20, 2023
 
   
 
   
|To prepare the interim space for Tower B occupants.
+
|To outline and separate the occupied space from the demolition and abatement activities.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/8/8f/CN50.1_Construction_Hoarding_Tower_B3_L01_L02F1.pdf Tower B3: Delineation and Hoarding Wall (L01 & L02)]'''
 +
|January 19, 2023
 +
 +
|To outline and separate the occupied space from the demolition and abatement activities.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/f/f6/CN29.2_Tower_Crane_Installation_Laurier-Tach%C3%A9_Parking_Garage.F2.pdf Tower Crane Installation in Laurier-Taché Parking Garage (UPDATED)]'''
 +
|January 19, 2023
 +
 +
|To prepare the site for the construction and installation of the tower crane (TC-2).
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/7/73/CN55_Tower_E_Construction_of_Partition_Wall.F1.V2.pdf Tower E: Construction of Partition Wall]'''
 +
|January 6, 2023
 +
 +
|To outline and separate the occupied space from the bulk of demolition and abatement activities while the Security Operations Centre remains in place (02B2-101).
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/a/aa/CN_56_Temporary_Disruption_to_Garage_Door_Openers.Canceled1.pdf Temporary Disruption to the Laurier-Taché Parking Garage Door Operators (CANCELED)]'''
 +
|January 3, 2023
 +
 +
|To remove, then relocate the fiber optic cables, including conduits and boxes that control the garage door openers within the Laurier-Taché parking garage. The conduits and boxes are currently located in L02 in Tower C on a block wall that is scheduled to be demolished.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/0/08/CN-42_Opening_of_Interim_Mailroom.F.pdf Opening of Interim Mailroom]'''
 +
|December 19, 2022
 +
 +
|To move the mailroom occupants from the old location in Tower B3 to the new location in Tower B2.
 +
Note: The old mailroom location is scheduled for demolition as part of phase 1 of the PDP3 AWR Project.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/8/82/CN27.2_Tower_B_Exterior_Civil_WorksF.pdf Tower B: Exterior Demolition (UPDATED)]'''
 +
|December 19, 2022
 +
 +
|To install temporary new stairs to allow emergency access and egress during construction activities and demolish existing stairs.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/4/47/CN52_Mobile_Crane_Preparation.F.pdf Preparation of the Mobile Crane Base]'''
 +
|December 14, 2022
 +
 +
|To prepare the base, a granular pad, for the installation of the mobile crane on Laurier Street, which is to assist with the installation of the Tower Crane (TC-2) within the exterior construction zone of Tower B.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/1/18/CN51_Temporary_Shutdown_of_Tower_C_Generator.F.pdf Tower C: Removal of Emergency Generator]'''
 +
|December 2, 2022
 +
 +
|To disconnect Tower C generator and then reconnect the feeds to the generators in Towers A and B to ensure backup electricity in the event of an electrical power outage.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/b/bb/CN47_Installation_Mobilization_of_Mobile_Platforms_in_Tower_C1_C2.F2.pdf Installation and Mobilization of Mast Climbers]'''
 +
|December 2, 2022
 +
 +
|To assist in the removal of the exterior envelope of Towwers C1/C2.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/c/c0/CN44_Temporary_Shutdown_of_Primary_Chilled_Water_Loop.F.Nov25.pdf Temporary Shutdown of Primary Chilled Water Loop (UPDATED)]'''
 +
|November 25, 2022
 +
 +
|To directly reconnect critical mechanical equipment (V-30, V-72 and V-74) to the primary chilled water loop to accommodate the demolition of the pumps and heat exchangers in Tower C Level 02. Space in the mechanical room is required for construction of the concrete shear wall and associated re-shoring.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/e/ec/CN49_Removal_of_Emergency_Generator_Tower_C.Bgis.pdf Tower C: Emergency Generator Removal]'''
 +
|November 18, 2022
 +
 +
|To disconnect the Tower C generator and then reconnect its emergency load to the generator control panel in Tower B to ensure backup electricity in the event of an electrical power outage.
 +
|-
 +
|'''[https://wiki.gccollab.ca/images/4/4c/CN41_Construction_Hoarding-Tower_B1-L0.R1Final.Nov17docx.pdf Tower B1 - Level 0: Construction Hoarding (UPDATED)]'''
 +
|November 17, 2022
 +
 +
|To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/1/17/Installation_of_Tower_Crane_in_Construction_Area.f.pdf Erection of Tower Crane (TC-1) in the construction area between PDP3 and PDP4 (Woodlands area)]'''
+
|'''[https://wiki.gccollab.ca/images/7/73/CN46_Demolition_Tower_B1_and_B3_%28L1_L2_L3%29F.Nov17.pdf Towers B1 & B3: Demolition and Construction Activities (L1, L2 & L3)]'''
|October 11, 2022
+
|November 17, 2022
 
   
 
   
|The erection of the tower crane (TC-1) is one of the PDP3 AWR Project milestones as it visually symbolizes the beginning of the demolition activities.
+
|To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/4/44/Tower_B1_Delineation_HoardingF.Bgis.pdf Towers A & B: Delineation and Hoarding Wall (L1, L2 and L3)]'''
+
|'''[https://wiki.gccollab.ca/images/8/84/CN45_Demolition_Tower_B1_and_B3_%28L6-L12%29.F.Nov17_%28002%29.pdf Towers B1 & B3: Demolition and Construction Activities (L6 to L12)]'''
|September 26, 2022
+
|November 17, 2022
 
   
 
   
|To outline and separate the occupied space in Tower A2 from the construction activities in Tower B1.  
+
|To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
 
|-
 
|-
|'''[https://wiki.gccollab.ca/images/5/50/Tower_B_Exterior_Civil_Works.F.pdf Tower B: Exterior Demolition]'''
+
|'''[https://wiki.gccollab.ca/images/1/17/Installation_of_Tower_Crane_in_Construction_Area.f.pdf Erection of Tower Crane (TC-1) in the construction area between PDP3 and PDP4 (Woodlands area)]'''
|September 20, 2022
+
|October 11, 2022
 
   
 
   
|To install temporary new stairs to allow, emergency access and egress during construction activities, and the demolition of the existing stairs. These enabling work activities are required to set up the ElissDon laydown area for construction.
+
|The erection of the tower crane (TC-1) is one of the PDP3 AWR Project milestones as it visually symbolizes the beginning of the demolition activities.
 
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/3/34/GOC479411_AWR_PDP3_-_Bicycle_Shelter_New_Location.Final.pdf Bicycle Enclosure Relocation]'''
 
|'''[https://wiki.gccollab.ca/images/3/34/GOC479411_AWR_PDP3_-_Bicycle_Shelter_New_Location.Final.pdf Bicycle Enclosure Relocation]'''
Line 133: Line 194:
 
   
 
   
 
|How to circulate between PDP4 and the A/B/E towers of PDP3 (interior).
 
|How to circulate between PDP4 and the A/B/E towers of PDP3 (interior).
|-
 
|'''[https://wiki.gccollab.ca/images/0/05/CN-23_Tree_Removal_at_Courcelette_and_Laurier_F.pdf Removal of Trees and Shrubs]'''
 
|August 22, 2022
 
 
|To prepare the area for the upcoming construction of the curtain wall mockup.
 
 
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/0/02/Laurier_Sidewalk_Closure_%28CN-24%29.pdf Sidewalk Closure: Laurier Street]'''
 
|'''[https://wiki.gccollab.ca/images/0/02/Laurier_Sidewalk_Closure_%28CN-24%29.pdf Sidewalk Closure: Laurier Street]'''
Line 148: Line 204:
 
   
 
   
 
|To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
 
|To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
|-
 
|'''[https://wiki.gccollab.ca/images/a/ad/PDP_IV_Sign_Reinstatement_%28CN-14%29.F.pdf PDP IV: Sign replacement]'''
 
|August 15, 2022
 
 
|To install the new PDP IV sign onto the exterior corner of the building, next to the Woodlands Area.
 
|-
 
|'''[https://wiki.gccollab.ca/images/d/d1/GOC479411-PDP_3_AWR-Critical_Spaces.F.pdf Mission Critical Spaces]'''
 
|August 2, 2022
 
 
|To complete A1 and A2 Towers construction fit up, to accommodate B1 Tower tenants.
 
 
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/d/dd/GOC479411_PDP_3_AWR_-_PDP_IV_Wayfinding.pdf Place du Portage IV: Wayfinding]'''
 
|'''[https://wiki.gccollab.ca/images/d/dd/GOC479411_PDP_3_AWR_-_PDP_IV_Wayfinding.pdf Place du Portage IV: Wayfinding]'''
Line 163: Line 209:
 
   
 
   
 
|To facilitate the construction renovations, including the Tower C Curtainwall Upgrades; Tower C Interior Upgrades; and Structural Upgrades for the Place du Portage AWR Project.
 
|To facilitate the construction renovations, including the Tower C Curtainwall Upgrades; Tower C Interior Upgrades; and Structural Upgrades for the Place du Portage AWR Project.
|-
 
|'''[https://wiki.gccollab.ca/images/1/1d/GOC479411-PDP_3_AWR-Tower_A_and_B_Delineation_Hoarding.F.pdf Towers A & B: Delineation and Hoarding Wall]'''
 
|August 2, 2022
 
 
|To outline and separate the occupied space in Tower A2 from the construction activities in Tower B1.
 
 
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/7/7c/Laurier-Tache_Parking_Garage_Closure-Maisonneuve.Aug2_FINAL.pdf Temporary Partial Closure: Laurier-Taché Parking Garage]'''
 
|'''[https://wiki.gccollab.ca/images/7/7c/Laurier-Tache_Parking_Garage_Closure-Maisonneuve.Aug2_FINAL.pdf Temporary Partial Closure: Laurier-Taché Parking Garage]'''
Line 178: Line 219:
 
   
 
   
 
|To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
 
|To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
|-
 
|'''[https://wiki.gccollab.ca/images/1/13/1-_Tower_A_and_B_Delineation_Hoarding.pdf Tower A and B Delineation Hoarding]'''
 
|July 14, 2022
 
 
|Outline and separate the occupied space in Tower A2 from the construction activities in Tower B1.
 
|-
 
|'''[https://wiki.gccollab.ca/images/c/c5/2-Interim_Mailroom_Demolition_and_Abatement.pdf Interim Mailroom Demolition and Abatement]'''
 
|July 14, 2022
 
 
|See notice
 
|-
 
|'''[https://wiki.gccollab.ca/images/3/3f/GOC479411-_PDP_3_AWR-_Construction_de_la_salle_de_courrier_provisoire.Bgis.pdf Interim Mailroom Construction]'''
 
|June 20, 2022
 
 
|See notice.
 
 
|-
 
|-
 
|'''[https://wiki.gccollab.ca/images/6/61/GOC479411-_PDP_3_AWR-_CM-_Avis_-_Maisonneuve.pdf Sidewalk and Lane Closure on Maisonneuve Boulevard]'''
 
|'''[https://wiki.gccollab.ca/images/6/61/GOC479411-_PDP_3_AWR-_CM-_Avis_-_Maisonneuve.pdf Sidewalk and Lane Closure on Maisonneuve Boulevard]'''
Line 198: Line 224:
 
   
 
   
 
|To facilitate the additional site logistics required for the CM and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
 
|To facilitate the additional site logistics required for the CM and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
|-
 
|'''[https://wiki.gccollab.ca/images/1/13/GOC479411-PDP_3_AWR-_CM-Tower_C_North_Couryard_Construction_Hoarding_C0_Communications_Notice.Final.pdf Construction Hoarding: Tower C - North Courtyard]'''
 
|May 24, 2022
 
 
|To facilitate the additional site logistics required for the Construction Manager and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
 
|-
 
|'''[https://wiki.gccollab.ca/images/5/5c/GOC479411-_PDP_3_AWR-_CM-Tower_B_Construction_Hoarding_Communications_Notice.Final.pdf Construction Hoarding: Tower B - Exterior]'''
 
|May 24, 2022
 
 
|To facilitate the additional site logistics required for the Construction Manager and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
 
|-
 
|'''[https://wiki.gccollab.ca/images/d/d7/1-_Construction_hoarding_activities.pdf Construction hoarding activities]'''
 
|April 6, 2022
 
 
|The main objective of the construction hoarding activities is to create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
 
|-
 
|'''[https://wiki.gccollab.ca/images/2/2c/2-Environmental_Soil_Study_Characterization.pdf Environmental Soil Study Characterization]'''
 
|April 5, 2022
 
 
|To help identify potential contaminants in the soil in and around the project area. Information gathered during this work will help describe the environmental quality of the soil.
 
|-
 
|'''[https://wiki.gccollab.ca/images/5/50/3-_Tree_Removal_Activities.pdf Tree Removal Activities]'''
 
|March 25, 2022
 
 
|To facilitate additional site logistics requirements for the Construction Manager (CM) to enable construction related activities in preparation of the PDP3 AWR Project and to update the landscape and riverfront greenbelt in connection to the complex.
 
|-
 
|'''[https://wiki.gccollab.ca/images/6/63/4-_Construction_hoarding_activities_%28Interim_space%29.pdf Construction hoarding activities (Interim space)]'''
 
|February 22, 2022
 
 
|To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
 
|-
 
 
|'''[https://wiki.gccollab.ca/images/5/5d/5-_Construction_hoarding_%28CM_site%29.pdf Construction hoarding (CM site)]'''
 
|February 17, 2022
 
 
|To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
 
|-
 
|'''[https://wiki.gccollab.ca/images/8/80/6-_Construction_hoarding.pdf Construction hoarding]'''
 
|February 11, 2022
 
 
|To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
 
|-
 
|'''[https://wiki.gccollab.ca/images/7/76/7-_Tree_removal_activities_%28Woodland_Area%29.pdf Tree removal activities (Woodland Area)]'''
 
|February 9, 2022
 
 
|To create an interim construction laydown area for the CM to enable construction related activities in preparation of the PDP3 AWR Project; and an opportunity to update the landscape and Riverfront Greenbelt connection to the complex.
 
 
|}
 
|}
 
<br>
 
<br>
 
<u><small>[[Place_du_Portage_III_Asset_and_Workplace_Renewal_Project| <i>Back to Welcome Page</I>]]</small></u><br>
 
<u><small>[[Place_du_Portage_III_Asset_and_Workplace_Renewal_Project| <i>Back to Welcome Page</I>]]</small></u><br>
 
</div>
 
</div>

Latest revision as of 15:25, 29 March 2023

IMPORTANT: Please note that this site has been replaced by the new PDP3 AWR Project Portal on GCpedia; no further updates will be made.

PDP3 Welcome Page1.jpg


Français


Project overview Project phases and milestones Objectives and benefits Notices to building occupants More information

Notices to tenants/occupants


Tenants of PDP3 and adjacent buildings have been informed of construction work through operational notices issued by BGIS, with PSPC’s informal consent. Notices issued to date are provided below. This list will be updated regularly.

Title (link) Release Date Purpose
Temporary Closure of Exterior Emergency Staircase March 16, 2023 To allow for investigations and repairs to the compromised structural slab in Tower A (L03).
Notice of Tower Crane (TC-2) Installation (UPDATED) March 13, 2023 To install a tower crane (TC-2) within the construction zone in front of Place du Portage III Tower B on Laurier Street.
Tower B1 & A2: Decoupling of Mechanical Systems March 13, 2023 To separate the mechanical systems in Tower A2 from Tower B1.
High Voltage Switchgear Component Replacement Feeding Tower C March 13, 2023 To perform needed maintenance to the High voltage Switchgear supplying power to Tower C.
Re-location of Switchgear Battery Room and Associated Equipment (UPDATED) March 10, 2023 To re-locate the batteries and associated equipment that support the Switchgear which provides power complex wide.
Tower B1: Delineation and Hoarding Wall (L5) February 24, 2023 To outline and separate the occupied space from the demolition and abatement activities.
Tower B1: Demolition and Construction Activities (L5) February 24, 2023 To complete Place du Portage III Asset and Workplace Renewal Project scheduled renovations.
Site Wayfinding QR Code February 16, 2023 To provide a quick and paperless link to wayfinding on Portage III and Portage IV's site as part of the Place du Portage III AWR Project.
Towers D & E: Delineation and Hoarding Wall (UDPATED) February 15, 2023 To outline and separate the occupied space from the demolition and abatement activities.
Electrical Shutdown in Laurier-Taché Parking Garage (Maisonneuve Sector) (UPDATED) February 8, 2023 To proceed with scheduled Tower C electrical maintenance.
Tower A: Storm and Sanitary Pipe Installation (UPDATED) February 3, 2023 To demolish the existing pipe and reinstall a new underground sanitary and storm one in L03 (A0314) in Tower A.
Tower Crane 2 (TC-2): Structural Steel Upgrades (UPDATED) January 27, 2023 To allow for the tower crane openings that are required for its erection in the Laurier-Taché Parking Garage through levels P1, P2 and P3.
Mission Critical Spaces (L15) January 27, 2023 To complete A1 and A2 Towers construction fit up, to accommodate B1 Tower tenants.
Tower B3: Delineation and Hoarding Wall (L0) January 20, 2023 To outline and separate the occupied space from the demolition and abatement activities.
Tower B3: Delineation and Hoarding Wall (L01 & L02) January 19, 2023 To outline and separate the occupied space from the demolition and abatement activities.
Tower Crane Installation in Laurier-Taché Parking Garage (UPDATED) January 19, 2023 To prepare the site for the construction and installation of the tower crane (TC-2).
Tower E: Construction of Partition Wall January 6, 2023 To outline and separate the occupied space from the bulk of demolition and abatement activities while the Security Operations Centre remains in place (02B2-101).
Temporary Disruption to the Laurier-Taché Parking Garage Door Operators (CANCELED) January 3, 2023 To remove, then relocate the fiber optic cables, including conduits and boxes that control the garage door openers within the Laurier-Taché parking garage. The conduits and boxes are currently located in L02 in Tower C on a block wall that is scheduled to be demolished.
Opening of Interim Mailroom December 19, 2022 To move the mailroom occupants from the old location in Tower B3 to the new location in Tower B2.

Note: The old mailroom location is scheduled for demolition as part of phase 1 of the PDP3 AWR Project.

Tower B: Exterior Demolition (UPDATED) December 19, 2022 To install temporary new stairs to allow emergency access and egress during construction activities and demolish existing stairs.
Preparation of the Mobile Crane Base December 14, 2022 To prepare the base, a granular pad, for the installation of the mobile crane on Laurier Street, which is to assist with the installation of the Tower Crane (TC-2) within the exterior construction zone of Tower B.
Tower C: Removal of Emergency Generator December 2, 2022 To disconnect Tower C generator and then reconnect the feeds to the generators in Towers A and B to ensure backup electricity in the event of an electrical power outage.
Installation and Mobilization of Mast Climbers December 2, 2022 To assist in the removal of the exterior envelope of Towwers C1/C2.
Temporary Shutdown of Primary Chilled Water Loop (UPDATED) November 25, 2022 To directly reconnect critical mechanical equipment (V-30, V-72 and V-74) to the primary chilled water loop to accommodate the demolition of the pumps and heat exchangers in Tower C Level 02. Space in the mechanical room is required for construction of the concrete shear wall and associated re-shoring.
Tower C: Emergency Generator Removal November 18, 2022 To disconnect the Tower C generator and then reconnect its emergency load to the generator control panel in Tower B to ensure backup electricity in the event of an electrical power outage.
Tower B1 - Level 0: Construction Hoarding (UPDATED) November 17, 2022 To create a safe delineation between tenants and the construction zone in preparation of the PDP3 AWR Project.
Towers B1 & B3: Demolition and Construction Activities (L1, L2 & L3) November 17, 2022 To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
Towers B1 & B3: Demolition and Construction Activities (L6 to L12) November 17, 2022 To complete Place du Portage III Asset and Workplace Renewal (PDP3 AWR) Project scheduled renovations.
Erection of Tower Crane (TC-1) in the construction area between PDP3 and PDP4 (Woodlands area) October 11, 2022 The erection of the tower crane (TC-1) is one of the PDP3 AWR Project milestones as it visually symbolizes the beginning of the demolition activities.
Bicycle Enclosure Relocation September 6, 2022 To facilitate the additional site logistics required for the Construction Manager to install exterior hoarding in preparation for construction work around PDP III Tower C.
Towers C and D Closure: Pedestrians Wayfinding Plans (Exterior) September 6, 2022 How to circulate between PDP4 and the A/B/E towers of PDP3 (exterior).
Towers C and D Closure: Pedestrians Wayfinding Plans (Interior) September 6, 2022 How to circulate between PDP4 and the A/B/E towers of PDP3 (interior).
Sidewalk Closure: Laurier Street August 16, 2022 To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
Traffic Lane Closure: Laurier Street August 16, 2022 To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is also to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
Place du Portage IV: Wayfinding August 2, 2022 To facilitate the construction renovations, including the Tower C Curtainwall Upgrades; Tower C Interior Upgrades; and Structural Upgrades for the Place du Portage AWR Project.
Temporary Partial Closure: Laurier-Taché Parking Garage August 2, 2022 To facilitate the following renovations: installation of a new elevator pit; an interruption in the ventilation system; structural upgrades; and replacement of underground piping.
Hoarding Wall: Tower B Exterior July 29, 2022 To facilitate the additional site logistics required for the Construction Manager (CM) to isolate the access to egress for site deliveries, loading and unloading. The implementation of this measure is to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.
Sidewalk and Lane Closure on Maisonneuve Boulevard May 24, 2022 To facilitate the additional site logistics required for the CM and to isolate the access to egress for site deliveries, loading and unloading. Additionally, the measures are required to ensure the safety and protection of the public and to contain the construction site within the hoarding walls.


Back to Welcome Page