The intent of the NFRC project is to relocate the channel conveying clean water of the North Fork of Rose Creek to remove it from and potential contaminated contact water seeping from the Faro waste rock piles. The design was completed by BGC Engineering for CIRNAC, and is being implemented by the ICM and their contractors who are selected through competitive processes. The first step of the project was the completion of the construction diversion channel which was completed by Pelly Construction over the winter of 2019, and was finished in early May 2019. An aerial UAV photo of the completed first phase of the project is below. | The intent of the NFRC project is to relocate the channel conveying clean water of the North Fork of Rose Creek to remove it from and potential contaminated contact water seeping from the Faro waste rock piles. The design was completed by BGC Engineering for CIRNAC, and is being implemented by the ICM and their contractors who are selected through competitive processes. The first step of the project was the completion of the construction diversion channel which was completed by Pelly Construction over the winter of 2019, and was finished in early May 2019. An aerial UAV photo of the completed first phase of the project is below. |