Phases du projet et étapes importantes
The project is divided into two (2) phases and consists of a complete overhaul of both the inside and outside of the building.
Phase 1 (from 2018 to 2024) is already underway. It will address the interior workplace refit of the western towers C1, C2, D and B3, and common base building systems throughout the complex.
Phase 2 (from 2022 to 2027) will address the interior workplace refit eastern towers A1, A2, B1, B2 and E.
Key milestones
• Planning and design activities for the PDP3 AWR Project started in 2018
• Selective interior demolition work of the western towers began in 2019 and was completed in 2021
• Construction activities started in early 2022
• The project is expected to be completed in 2027