FSII-NTTO Reference Implementation / Mises en oeuvre de référence IISP-OTTN

Last Updated: September 30, 2019
RI Scope Deployment Date Milestone Dates Testing Resources Comments Detailed Notes Action Items Title Archive
25.0-part1

25.0-part2

NinJo 3.4 (WPR1.5, Tsunami) + Scribe RI25. 0-part1: September 24, 2019 (excluding NinJo 3.4). Deployment completed.

RI25. 0-part2: NinJo 3.4: DELAYED until November 13, 2019

RI25.0-part1 deployment completed.

RI25.0-part2 is ready for deployment but is dependant on the 18.04 IFW being deployed first.

Testing completed. Synopsis: RI25.0-part1 (Scribe. WxO, WeatherCAN, DMS) was deployed on September 24.

RI Notes:  RI25.0-part2 (NinJo 3.4) is delayed given delay in 18.04 IFW deployment.

.

1. RI Planning/Scoping/Components: NinJo 3.4 MSC config release (including WPR-O Release 1.5 and deployment of Tsunami alerts in MWAS) plus changes to Scribe.

2. RI Testing: Testing completed.

3. RI Deployment: RI25.0-part1 (Scribe. WxO, WeatherCAN, DMS) was deployed on September 24. RI25.0-part2 (NinJo 3.4) is delayed given delay in 18.04 IFW deployment.

4. RI Dependencies: NinJo 3.4 must be deployed on 18.04 IFW.

5. Risks:

- Further delays in IFWUU could continue to delay deployment of NinJo 3.4.

25.0 No
25.1 Aviation Changes October 10, 2019 1. wxapps-beta testing: Sep 25-Oct 2, 2019

2. wxapps-stage testing: Oct 2-9, 2019

1. CMAC's

2. NTTO

Synopsis: Aviation program changes plus some minor wxapps config changes.

RI Notes: Beta testing in progress. Packages have been installed on wxapps-beta servers. RI changed to 24.6 given delay in 18.04 IFW.

1. RI Planning/Scoping/Components:

2. RI Testing: Beta testing in progress. Packages have been installed on wxapps-beta servers.

3. RI Deployment: Standard deployment on wxapps (ops) systems. Any RTAF changes will be managed by CMAC offices.

4. RI Dependencies: None identified.

5. Risks: None identified.

25.1 No
25.X URP 2.13.2 Oct 29, 2019 Package submission: Sep 30, 2019

1. Beta: now - Sep 30

2. Integration: Oct 1 - 11

3. UAT: Oct 14 - 25

1. URP dev team

2. NTTO

3. PSD

a. Removal of all decommissioned C and X-bands

b. Promotion of the remaining S-bands to Primary for SWP

1. RI Planning/Scoping/Components: Development is on track.

2. RI Testing: Will be conducted on CMC urpx dev1 servers.

3. RI Deployment: TBD

4. RI Dependencies: None.

25.2 No
25.X IFW Ubuntu Upgrade (IFWUU) **DELAYED** Completed by the week of Oct 28-31, 2019 Live UAT in progress on 18.04 IFW's (ops01/cmac01) All forecasters Synopsis: Upgrade of IFW from Ubuntu12.04 to 18.04. Includes renaming of all IFW's according to new national SSC standard and 18.04 release of URP-IV (to accommodate 6 minute S-band data).

RI Notes: Blocker display issues have resulted in delay of deployment. SSC are dedicating significant resources in an attempt to resolve these display issues. NTTO are meeting weekly with RI managers and PSH to provide updates and discuss issues.

1. RI Planning/Scoping/Components:

- Upgrade 12.04 IFW to KDE 18.04.

- Renaming of all IFW's according to new national SSC standard. https://ecollab.ncr.int.ec.gc.ca/theme/pnp-npp/priv/RI/RIAdmin/18.04-IFW-Names.xlsx

- Maintain user accounts

- 18.04 release of URP-IV (2.4.0) client to accommodate 6 minute S-band data. 19693.

2. RI Testing: Live UAT in progress.

3. RI Deployment: Blocker display issues have resulted in delay of deployment. SSC are dedicating significant resources in an attempt to resolve these display issues. NTTO are meeting weekly with RI managers and PSH to provide updates and discuss issues.  SSC estimates it will take 1-2 hours to complete upgrade each IFW. The plan is to upgrade 2 IFW's at a time per office but multiple offices can be updated at the same time.

4. RI Dependencies: RI25.0 NinJo 3.4 deployment requires that the 18.04 IFW be deployed first.

5. Risks:

a. It is not certain if SSC will be able to resolve all display issues.

b. Ability to ensure all forecasters get 18.04 IFW setup before full deployment.

1. NTTO to setup deployment meeting. 25.3 No
25.X IFW Desktop Box (CPU) Upgrade Starting late fall 2019 TBD TBD Synopsis: Upgrade of NinJo CPU boxes to Ubuntu 18.04.

RI Notes: Contact project lead Krysta-Lee Clifford for information. NTTO will coordinate testing and deployment.

1. RI Planning/Scoping/Components: Upgrade of NinJo CPU boxes to Ubuntu 18.04. Contact project lead Krysta-Lee Clifford for information. NTTO will coordinate testing and deployment.  2. RI Testing: Plan it to setup test box (connected to 18.04 IFW) in each office. Once test system is stable, the testing can be expanded to a live UAT which would include one box/18.04 IFW pair in each office.  

3. RI Deployment: May take several months to complete on all systems.

4. RI Dependencies: None identified.

25.3 No
25.X Aviation Changes December 5, 2019 TBD TBD Synopsis: Aviation program changes.

RI Notes: NTTO are awaiting RFI submission

1. RI Planning/Scoping/Components: Aviation program changes. NTTO are awaiting RFI submission.

2. RI Testing: Standard RI testing process with testing starting on wxapps-beta and progressing to wxapps-stage.

3. RI Deployment: Standard deployment on wxapps (ops) systems. Any RTAF changes will be managed by CMAC offices.

4. RI Dependencies: None identified.

5. Risks: None identified.

25.3 No
25.X Scribe January, 2020 Beta: TBD.

Integration: TBD.

UAT: TBD.

TBD Synopsis: Intermediate RI for Scribe config changes:

- Realign NAVTEX areas

- Configure Quebec meso-regions in Public Scribe  

RI Notes: Navtex realignment: The Canadian Coast Guard (CCG) has requested modifications to the FQCN3x/9x NAVTEX bulletins.

1. RI Planning/Scoping/Components: Intermediate RI for Scribe config changes:

- Realign NAVTEX areas

https://ecollab.ncr.int.ec.gc.ca/theme/165/RFI/CIC-2019-RFI003-ScribeMarine-NAVTEX-Realignment.docx.

- Configure Quebec meso-regions in Public Scribe

https://ecollab.ncr.int.ec.gc.ca/theme/165/RFI/CIC-QR-2019-RFI015-ScribePublic-SITS648-Add-Meso-Regions.docx. The Canadian Coast Guard (CCG) has requested modifications to the FQCN3x/9x NAVTEX bulletins.  

2. RI Testing: Standard Scribe testing on wxapps-beta/stage systems.

3. RI Deployment: TBD.

4. RI Dependencies: None identified.

5. Risks: None identified.

25.4 No
25.X Upgrade NinJo servers to 18.04 January 2020 Synopsis: Upgrade NinJo servers to Ubuntu 18.04.

RI Notes: In planning phase only.

1. RI Planning/Scoping/Components: Upgrade NinJo servers to Ubuntu 18.04.

2. RI Testing: TBD

3. RI Deployment: TBD

4. RI Dependencies: TBD

25.5 No
25.X Aviation Changes January 30, 2020 TBD TBD Synopsis: Aviation program changes.

RI Notes: NTTO are awaiting RFI submission.

1. RI Planning/Scoping/Components: Aviation program changes. NTTO are awaiting RFI submission.

2. RI Testing: Standard RI testing process with testing starting on wxapps-beta and progressing to wxapps-stage.

3. RI Deployment: Standard deployment on wxapps (ops) systems. Any RTAF changes will be managed by CMAC offices.

4. RI Dependencies: None identified.

5. Risks: None identified.

25.6 No
25.X Edigraf Ubuntu Upgrade March 11, 2020 TBD TBD Synopsis: Upgrade of Edigraf to Ubuntu 18.04

RI Notes: In RI planning phase only. Project information can be found at: http://dvwiki.science.gc.ca/wiki/Edigraf_port_project

1. RI Planning/Scoping/Components: Upgrade of Edigraf to Ubuntu 18.04. Project information can be found at: http://dvwiki.science.gc.ca/wiki/Edigraf_port_project

2. RI Testing: TBD

3. RI Deployment: The new servers will be hosted on VM containers. - Data feeds to be handled by Sarracenia - All applications and configurations to be deployed to servers via Debian packages. - Incoming model data and processing to be standardized - Ensure that current contingency plans are carried over to the new configuration 4. RI Dependencies: Edigraf is dependent on forecast model fields.  SPI (software at CMC) will be replacement for MAX. MSI (Multi Spectral Imagery) will be generated at CMC (migrated from local offices).

25.7 No
25.X Aviation Changes March 26, 2020 TBD TBD Synopsis: Aviation program changes.

RI Notes: NTTO are awaiting RFI submission.

1. RI Planning/Scoping/Components: Aviation program changes. NTTO are awaiting RFI submission.

2. RI Testing: Standard RI testing process with testing starting on wxapps-beta and progressing to wxapps-stage.

3. RI Deployment: Standard deployment on wxapps (ops) systems. Any RTAF changes will be managed by CMAC offices.

4. RI Dependencies: None identified.

5. Risks: None identified.

25.8 No
25.X URP 2.14 March 31, 2020 Package submission: February 21, 2020

1. Integration: Feb 27-March 13, 2020 2. UAT: March 16-27, 2020

1. FSII only

2. 1 (3h)

Synopsis: ​URP 2.14. Primary changes include:

• Dual pol particle classification & QPE products

• Other algorithm improvements

• 2020 radar configurations 

RI Notes: In planning phase.

1. RI Planning/Scoping/Components: URP 2.14. Primary changes include:

• Dual pol particle classification & QPE products

• Other algorithm improvements

• 2020 radar configurations

2 Testing: TBD

3. RI Deployment: TBD

4. RI Dependencies: TBD

25.9 No
25.X Aviation Changes May 21, 2020 TBD TBD Synopsis: Aviation program changes.

RI Notes: NTTO are awaiting RFI submission.

1. RI Planning/Scoping/Components: Aviation program changes. NTTO are awaiting RFI submission.

2. RI Testing: Standard RI testing process with testing starting on wxapps-beta and progressing to wxapps-stage.

3. RI Deployment: Standard deployment on wxapps (ops) systems. Any RTAF changes will be managed by CMAC offices.

4. RI Dependencies: None identified.

5. Risks: None identified.

25.91 No
26.0 NinJo 4.3 (TAF Editor) + Scribe June 1, 2020 Scribe packages: February 21, 2020 (for Beta)

NinJo packages: March 25, 2020 (for Integration) Beta: Feb 26-March 18, 2020 Integration: March 30-April 28, 2020 UAT: May 7-14, 2020

1. FSII only. CMAC for TAF Editor.

2. 1 (2d)

3. 1 (3h)

Synopsis: ​NinJo 4.3 (TAF Editor) + Scribe

RI Notes: Full deployment and operational activation of  TAF Editor (including integration of autoTAF data into TAF Editor).

1. RI Planning/Scoping/Components: NinJo 4.3 + Scribe. Full deployment and operational activation  of TAF Editor (including integration of autoTAF data into TAF Editor).

2 Testing: TBD

3. RI Deployment: TBD

4. RI Dependencies: TBD

26.0 No
27.0 NinJo 4.X + Scribe October 27, 2020 Scribe packages: July 23, 2020 (for Beta)

NinJo packages: August 31, 2020 (for Integration) Beta: June 28-Aug 24, 2020 Integration: Sep 3-24, 2020 UAT: Oct 5-9, 2020

1. FSII only

2. 1 (2d)

3. 1 (3h

Synopsis: ​NinJo 4.X + Scribe

RI Notes: NinJo config release plus Scribe enhancements and program change requests.

1. RI Planning/Scoping/Components: NinJo 4.X + Scribe. NinJo config release plus Scribe enhancements and program change requests. 

2. Testing: TBD 3. RI Deployment: TBD 4. RI Dependencies: TBD

27.0 No
Test Cases RI Related Info Lists Contingency
RI Documents RI Summary Post RI Testing
RI Timelines RI Summary Archive QMS/ISO Supporting Documentation
Release Geography Changes Testing Systems
Supporting Documentation Links
Document Archive Contacts
Routing Table Change Requests
NTTO Team Calendar