Departmental Journey[edit | edit source]

Prioritization[edit | edit source]

Legacy data centres.png
Assess Legacy Data Centres
Data centre closures.png
Recommend Priority Data Centre Closures
Gate.png
Gate 1: GC EARB Endorsement of DC Closures


Notify.png
Notify Impacted Departments
MoU.png
MoU for funds to support departmental discovery




Discovery[edit | edit source]

Application Portfolio Analysis
Modernization vision.png
Determine modernization vision for organization
Rationalization.png
Determine rationalization opportunities
Doc migration.png
Document migration strategy and target (cloud or DC) in APM


Engage.png
Engage SSC PM and WLM Factory suppliers
Doc milestones.png
Document Project Milestones


Doc cost estimates.png
Document Cost Estimates
Oversight.png
TBS Oversight Team review of costs, plan, and portfolio analysis
Gate.png
Gate 2: GC EARB Endorsement. MoU to Release Execution Funds



Execution[edit | edit source]

Legacy data centres.png
Staff project team
Data centre closures.png
Configure Cloud Platform
(e.g. Landing Zone)
Gate.png
Launch Security Assessment & Authorization process


Notify.png
Develop test plans
MoU.png
Execute migrations, security assessments, & testing


MoU.png
Report status to TBS Oversight Team


MoU.png
Decommission legacy data centre