Application Modernization


Departmental Journey

Prioritization

Legacy data centres.png
Assess Legacy Data Centres
Data centre closures.png
Recommend Priority Data Centre Closures
Gate.png
Gate 1: GC EARB Endorsement of DC Closures


Notify.png
Notify Impacted Departments
MoU.png
MoU for funds to support departmental discovery




Discovery

Application Portfolio Analysis
Modernization vision.png
Determine modernization vision for organization
Rationalization.png
Determine rationalization opportunities
Doc migration.png
Document migration strategy and target (cloud or DC) in APM


Engage.png
Engage SSC PM and WLM Factory suppliers
Doc milestones.png
Document Project Milestones


Doc cost estimates.png
Document Cost Estimates
Oversight.png
TBS Oversight Team review of costs, plan, and portfolio analysis
Gate.png
Gate 2: GC EARB Endorsement. MoU to Release Execution Funds



Execution

Staff team.png
Staff project team
Cloud platform.png
Configure Cloud Platform
(e.g. Landing Zone)
Launch security.png
Launch Security Assessment & Authorization process


Test plans.png
Develop test plans
Execute.png
Execute migrations, security assessments, & testing


Report status.png
Report status to TBS Oversight Team


Legacy data centres.png
Decommission legacy data centre



Discovery

Application Porfolio Analysis

Determine Modernization Vision for the Organization

By the end of this step, you should have discussed with leadership how far you want to take your modernization journey. This will be the vision for your organization. Those who will be performing the subsequent portfolio analysis steps should understand that vision.

This is an opportunity to determine the direction for the organization; is it to largely sustain current operations and culture, or does the organization desire to modernize and be more transformative. Perhaps your organization has already begun a modernization journey. In today's IT environment cloud technologies combined with DevOps methods are having a large impact on how IT is delivered. Amongst the goals of these technologies and methods is to decrease lead time and time to market; in summary

  • deliver IT faster
  • Increase reliability
  • Increase security
  • Increase quality

This guide does not instruct an organization how to undertake its modernization journey, but instead meant to be a catalyst for establishing the vision. These changes can be wide sweeping impacting roles, responsibilities, and culture. They are not undertaken in a year, but instead must be seen as a journey of maturity and continuous improvement.

While some organizations have started this journey years ago and are ready to go "all in" on cloud and the workforce are DevOps practitioners, others have not begun the journey.

For those who have not yet begun a modernization journey the choice may be take this opportunity to start that journey. For others, they may decide to simply sustain operations as-is.

cloud maturity map will be inserted here

A simple visual for plotting you cloud adoption maturity can be found here. Most organizations start small with a few low risk applications. A team of willing and keen developers from within your existing workforce would lead an imitative to migrate those low risk workloads to the cloud. From these experiences they would use their learnings to train others to do the same. As the number of workloads grow, the need for more sophisticated methods such as automation and DevOps will need to be applied. This will facilitate scaling without impacting agility. Existing governance and roles will also need to evolve. An organization should review the [insert roles and reap document here] to ensure your organization is ready to undertake the required roles to support cloud services.

A simple scorecard has been devised to assess low risk workloads for cloud migration. This scorecard is meant to provide you a short list from which to further decide where to start. Any application can be migrated to the cloud with enough time and effort. The scorecard is meant to identify low risk and low effort migrations.

For organizations that desire to forego modernization opportunities, the decision to rehost the entire application portfolio to a new data centre provides that opportunity.

Determine Rationalization Opportunities

Document Migration Strategy and Targets

Strategy Short Description Full Description Data Centre Cloud
Retire Decomission Decomission the application.
Rehost Lift and shift ? X X
Replatform Lift, shift, and tinker ? X X
Refactor Re-architect ? X X
Replace Repurchase ? X X