Changes

no edit summary
Line 42: Line 42:     
• Planning and design activities for the PDP3 AWR Project started in 2018  <br>
 
• Planning and design activities for the PDP3 AWR Project started in 2018  <br>
• Selective interior demolition work of the western towers began in 2019 and was completed in fall 2021<br>
+
• Selective interior demolition work of the western towers began in 2019 and was completed in 2021<br>
 
• Construction activities started in early 2022 <br>
 
• Construction activities started in early 2022 <br>
 
• The project is expected to be completed in 2027 <br>
 
• The project is expected to be completed in 2027 <br>
238

edits