Changes

no edit summary
Line 224: Line 224:  
|-
 
|-
 
|'''ISSUE'''
 
|'''ISSUE'''
|Ongoing application assessments show that teams with applications/systems dependent on SCED/Oracle DBs are choosing not to prepare for migration at this time, causing significant delays to the migration schedule.
+
|The team has recently lost two resources, who were the only automation resources, which means the team is currently unable to deliver on its planned workload migration schedule.
 
|-
 
|-
 
|'''Impact'''
 
|'''Impact'''
Line 230: Line 230:  
|-
 
|-
 
|'''Resolution Plan'''
 
|'''Resolution Plan'''
|Acquire OCI to provide Oracle solutions in the Cloud, and continue to use the Application Prioritization Framework to assess readiness for migration.
+
|Escalate to executive team to secure necessary resources and re-prioritize workload.
 
|}
 
|}
   Line 236: Line 236:  
|-
 
|-
 
|'''ISSUE'''
 
|'''ISSUE'''
|Given the current project constraints, such as SCED, Oracle, stakeholder and resource availability, and the loss of two key resources, we will not be able to meet our forecast milestone dates.
+
|Identify critical success factors to prioritize workload then communicate new direction to all key stakeholders.
 
|-
 
|-
 
|'''Impact'''
 
|'''Impact'''
Line 242: Line 242:  
|-
 
|-
 
|'''Resolution Plan'''
 
|'''Resolution Plan'''
|Create and implement stakeholder engagement plan, and attempt to secure backfill for the loss of two key resources.
+
|Create and implement stakeholder engagement plan.
 
|}
 
|}
   Line 248: Line 248:  
|-
 
|-
 
|'''ISSUE'''
 
|'''ISSUE'''
|Create approach to engage Enterprise Architects (EAs) in identifying migration vs modernization candidates for moving applications/platforms to the Cloud.
+
|Ongoing application assessments show that teams with applications/systems dependent on SCED/Oracle DBs are choosing not to prepare for migration at this time, causing significant delays to the migration schedule.
 
|-
 
|-
 
|'''Impact'''
 
|'''Impact'''
|Medium
+
|High
 
|-
 
|-
 
|'''Resolution Plan'''
 
|'''Resolution Plan'''
|EAs are currently being engaged to address this issue.
+
|Acquire OCI to provide Oracle solutions in the Cloud, and continue to use the Application Prioritization Framework to assess readiness for migration.
 
|}
 
|}
  
510