Line 168: Line 168:  
|-
 
|-
 
|'''RISK'''
 
|'''RISK'''
|If the SCED pilot for PGS and eBIDA takes longer than expected, then SCED implementation for 370+ other applications/platforms by March 2023 may be delayed.
+
|If the SCED re-architecture goes ahead, then SCED implementation for 370+ other applications/platforms by March 2023 may be delayed.
 
|-
 
|-
 
|'''Impact'''
 
|'''Impact'''
Line 198: Line 198:  
|-
 
|-
 
|'''RISK'''
 
|'''RISK'''
|If application/platform teams do not have enough capacity, then workload migration to the Cloud stalls, delaying the project schedule.
+
|If there is not enough Cloud expertise and capacity on application/platform teams, then workload migration to the Cloud stalls, delaying the project schedule.
 
|-
 
|-
 
|'''Impact'''
 
|'''Impact'''
Line 207: Line 207:  
|-
 
|-
 
|'''Mitigation'''
 
|'''Mitigation'''
|Engage each application/platform team early in the process and escalate accordingly if there is not enough capacity.
+
|Engage each application/platform team early in the process, secure temporary Cloud expertise, and escalate accordingly if there is not enough capacity.
 
|}
 
|}
  