Changes

Line 57: Line 57:  
|2020-04-30
 
|2020-04-30
 
|
 
|
|TC had requested an  initial target date of July 2018 per the SCED project but is not scheduled to have secure connectivity until April 2020. Until the SCED is available, TC cannot put into production any Cloud applications that require connectivity to an Enterprise data centre.
+
|TC requested a target date of July 2018 per the SCED project but is not scheduled to have secure connectivity until April 2020. Until SCED is available, TC cannot put into production any Cloud applications that require connectivity to a Data Centre.
 
|-
 
|-
 
|Cloud  Foundation Build  
 
|Cloud  Foundation Build  
Line 65: Line 65:  
|Complete (except for SCED secure connectivity). This is the Cloud working environment for TC applications.
 
|Complete (except for SCED secure connectivity). This is the Cloud working environment for TC applications.
 
|-
 
|-
|Sprint #1
+
|Sprint #1 Migration of Applications to Cloud
 
|2020-01-31
 
|2020-01-31
 
|2020-01-31
 
|2020-01-31
Line 77: Line 77:  
|
 
|
 
|-
 
|-
|Sprint #2
+
|Sprint #2 Migration of Applications to Cloud
 
|2020-02-28
 
|2020-02-28
 
|TBD
 
|TBD
510

edits