Difference between revisions of "Place du Portage III AWR Project phases and milestones"
Layal.eshak (talk | contribs) |
Layal.eshak (talk | contribs) |
||
Line 35: | Line 35: | ||
The project is divided into two phases and consists of a complete overhaul of both the inside and outside of the building. <br> | The project is divided into two phases and consists of a complete overhaul of both the inside and outside of the building. <br> | ||
<br> | <br> | ||
− | <b>Phase 1</b> (from 2018 to | + | <b>Phase 1</b> (from 2018 to 2027) is underway. It will address the interior workplace refit of the western towers (C1, C2, D and B3) by 2024, and common base building systems throughout the complex by 2027. |
<br><br> | <br><br> | ||
− | <b>Phase 2</b> (from | + | <b>Phase 2</b> (from 2024 to 2027) will address the interior workplace refit eastern towers (A1, A2, B1, B2 and E). |
<br><br> | <br><br> | ||
<b>Key milestones</b><br> | <b>Key milestones</b><br> |
Revision as of 12:31, 6 June 2022
Français |
Project overview | Project phases and milestones | Objectives and benefits | Notices to building occupants | More information |
Project phases and milestones
The project is divided into two phases and consists of a complete overhaul of both the inside and outside of the building.
Phase 1 (from 2018 to 2027) is underway. It will address the interior workplace refit of the western towers (C1, C2, D and B3) by 2024, and common base building systems throughout the complex by 2027.
Phase 2 (from 2024 to 2027) will address the interior workplace refit eastern towers (A1, A2, B1, B2 and E).
Key milestones
• Planning and design activities for the PDP3 AWR Project started in 2018
• Selective interior demolition work of the western towers began in 2019 and was completed in 2021
• Construction activities started in early 2022
• The project is expected to be completed in 2027