Important: The GCConnex decommission will not affect GCCollab or GCWiki. Thank you and happy collaborating!
Difference between revisions of "Place du Portage III AWR Project phases and milestones"
Layal.eshak (talk | contribs)  | 
				Layal.eshak (talk | contribs)   | 
				||
| Line 5: | Line 5: | ||
<!--French-->  | <!--French-->  | ||
{| class="FCK__ShowTableBorders" style="border:white solid 1px; background-color:#551155" width="10%" align="center"  | {| class="FCK__ShowTableBorders" style="border:white solid 1px; background-color:#551155" width="10%" align="center"  | ||
| − | | style="padding-right: 5px; padding-left: 5px; padding-bottom: 10px; padding-top: 10px; text-align: center;" | [[  | + | | style="padding-right: 5px; padding-left: 5px; padding-bottom: 10px; padding-top: 10px; text-align: center;" | [[Renouvellement_de_Portage_III_Phases_du_projet_et_étapes_importantes|<span style="color:#ffffff"> '''Français'''</span>]]    | 
|} <br>  | |} <br>  | ||
Revision as of 19:11, 21 April 2022

| Français | 
| Project overview | Project phases and milestones | Objectives and benefits | Notices to building occupants | More information | 
Project phases and milestones
The project is divided into two (2) phases and consists of a complete overhaul of both the inside and outside of the building. 
 
Phase 1 (from 2018 to 2024) is already underway. It will address the interior workplace refit of the western towers C1, C2, D and B3, and common base building systems throughout the complex.
Phase 2 (from 2022 to 2027) will address the interior workplace refit eastern towers A1, A2, B1, B2 and E.
Key milestones
 
•	Planning and design activities for the PDP3 AWR Project started in 2018  
•	Selective interior demolition work of the western towers began in 2019 and was completed in 2021
•	Construction activities started in early 2022 
•	The project is expected to be completed in 2027 