• Planning and design activities for the PDP3 AWR Project started in 2018 <br> | • Planning and design activities for the PDP3 AWR Project started in 2018 <br> | ||
− | • Selective interior demolition work of the western towers began in 2019 and was completed in | + | • Selective interior demolition work of the western towers began in 2019 and was completed in 2021<br> |
• Construction activities started in early 2022 <br> | • Construction activities started in early 2022 <br> | ||
• The project is expected to be completed in 2027 <br> | • The project is expected to be completed in 2027 <br> |
Revision as of 16:10, 21 April 2022
Français |
Project overview | Project phases and milestones | Objectives and benefits | Notices to building occupants | More information |
Project phases and milestones
The project is divided into two (2) phases and consists of a complete overhaul of both the inside and outside of the building.
Phase 1 (from 2018 to 2024) is already underway. It will address the interior workplace refit of the western towers C1, C2, D and B3, and common base building systems throughout the complex.
Phase 2 (from 2022 to 2027) will address the interior workplace refit eastern towers A1, A2, B1, B2 and E.
Key milestones
• Planning and design activities for the PDP3 AWR Project started in 2018
• Selective interior demolition work of the western towers began in 2019 and was completed in 2021
• Construction activities started in early 2022
• The project is expected to be completed in 2027