Difference between revisions of "Place du Portage III AWR Project phases and milestones"
Jump to navigation
Jump to search
Layal.eshak (talk | contribs) |
Layal.eshak (talk | contribs) |
||
Line 37: | Line 37: | ||
<b>Phase 1</b> (from 2018 to 2024) is already underway. It will address the interior workplace refit of the western towers C1, C2, D and B3, and common base building systems throughout the complex. | <b>Phase 1</b> (from 2018 to 2024) is already underway. It will address the interior workplace refit of the western towers C1, C2, D and B3, and common base building systems throughout the complex. | ||
<br><br> | <br><br> | ||
− | <b>Phase 2</b>(from 2022 to 2027) will address the interior workplace refit eastern towers A1, A2, B1, B2 and E. | + | <b>Phase 2</b> (from 2022 to 2027) will address the interior workplace refit eastern towers A1, A2, B1, B2 and E. |
<br><br> | <br><br> | ||
<b>Key milestones</b><br> | <b>Key milestones</b><br> |
Revision as of 11:09, 20 April 2022
Français |
Project overview | Project phases and milestones | Objectives and benefits | Notices to building occupants | More information |
Project phases and milestones
The project is divided into two (2) phases and will consist of renovations to the inside and the outside of the building.
Phase 1 (from 2018 to 2024) is already underway. It will address the interior workplace refit of the western towers C1, C2, D and B3, and common base building systems throughout the complex.
Phase 2 (from 2022 to 2027) will address the interior workplace refit eastern towers A1, A2, B1, B2 and E.
Key milestones
• Planning and design activities for the PDP3 AWR Project started in 2018
• Selective interior demolition work of the western towers began in 2019 and was completed in fall 2021
• Construction activities started in early 2022
• The project is expected to be completed in 2027