Difference between revisions of "Place du Portage III AWR Project phases and milestones"
Jump to navigation
Jump to search
Layal.eshak (talk | contribs) (Created page with "<!--765e--> center|link= <br> <!--French--> {| class="FCK__ShowTableBorders" style="border:white solid 1px; background-color:#551155" width="...") |
Layal.eshak (talk | contribs) |
||
Line 46: | Line 46: | ||
• The project is expected to be completed in 2027 <br> | • The project is expected to be completed in 2027 <br> | ||
<br><br> | <br><br> | ||
− | <u><small>[[ | + | <u><small>[[Place_du_Portage_III_Asset_and_Workplace_Renewal_Project| <i>Back to Welcome Page</I>]]</small></u><br> |
</div> | </div> | ||
}} | }} | ||
</div> | </div> | ||
</div> | </div> |
Revision as of 08:54, 20 April 2022
Français |
Project overview | Project phases and milestones | Objectives and benefits | Notices to building occupants | More information |
Project phases and milestones
The project is divided into two (2) phases and will consist of renovations to the inside and the outside of the building.
Phase 1 (from 2018 to 2024) is already underway. It will address the interior workplace refit of the western towers C1, C2, D and B3, and common base building systems throughout the complex.
Phase 2(from 2022 to 2027) will address the interior workplace refit eastern towers A1, A2, B1, B2 and E.
Key milestones
• Planning and design activities for the PDP3 AWR Project started in 2018
• Selective interior demolition work of the western towers began in 2019 and was completed in fall 2021
• Construction activities started in early 2022
• The project is expected to be completed in 2027