Difference between revisions of "NTTO"

From wiki
Jump to navigation Jump to search
(Added Calendar and RI Summary Table)
(Replaced content with "Contents of this page have been removed and will be relocated in the near future.")
Tag: Replaced
 
(24 intermediate revisions by the same user not shown)
Line 1: Line 1:
= '''<u>FSII-NTTO Reference Implementation / Mises en oeuvre de référence IISP-OTTN</u>''' =
+
Contents of this page have been removed and will be relocated in the near future.
[[File:RI-Calendar-2019-09-19.png|center|frameless|907x907px]]
 
{| class="wikitable"
 
|+
 
!RI
 
!Scope
 
!Deployment Date
 
!Milestone Dates
 
!Testing Resources
 
!Comments
 
!Detailed Notes
 
!Action Items
 
!Title
 
!Archive
 
|-
 
|'''24.6'''
 
|IFW Ubuntu Upgrade (IFWUU)
 
|Sep 30-Oct 3, 2019
 
|Live UAT on 18.04 IFW's (ops01/cmac01): Ongoing until Sep 27, 2019
 
|All forecasters
 
|Synopsis: Upgrade of IFW from Ubuntu12.04 to 18.04. Includes renaming of all IFW's according to new national SSC standard and 18.04 release of URP-IV (to accommodate 6 minute S-band data).
 
 
 
RI Notes: Forecasters in each office are instructed to evaluate and setup 18.04 IFW as part of live UAT and before full operational deployment.  NTTO have setup weekly meetings with RI managers to discuss issues.
 
|1. RI Planning/Scoping/Components:
 
 
 
- Upgrade 12.04 IFW to KDE 18.04.
 
 
 
- Renaming of all IFW's according to new national SSC standard. <nowiki>https://ecollab.ncr.int.ec.gc.ca/theme/pnp-npp/priv/RI/RIAdmin/18.04-IFW-Names.xlsx</nowiki>
 
 
 
- Maintain user accounts
 
 
 
- 18.04 release of URP-IV (2.4.0) client to accommodate 6 minute S-band data. 19693.
 
 
 
2. RI Testing: Live UAT in progress. Forecasters in each office are instructed to evaluate and setup/configure/personalize 18.04 IFW before full operational deployment.  NTTO have setup weekly meetings with RI managers to discuss issues.
 
 
 
3. RI Deployment: Deployment will need to be staggered over several days give large number of IFW's to upgrade.  SSC estimates it will take 1-2 hours to complete upgrade each IFW. The plan is to upgrade 2 IFW's at a time per office but multiple offices can be updated at the same time.
 
 
 
4. RI Dependencies: RI25.0 NinJo 3.4 deployment requires that the 18.04 IFW be deployed first.
 
 
 
5. Risks:
 
 
 
a. Live UAT may uncover blocker issues not discovered during previous testing.
 
 
 
b. Ability to ensure all forecasters get 18.04 IFW setup before full deployment.
 
|1. NTTO to setup deployment meeting.
 
|24.6
 
|No
 
|-
 
|'''24.7'''
 
|Aviation Changes
 
|October 10, 2019
 
|RFI submission: Sep 10, 2019
 
 
 
Package submission: Sep 20, 2019
 
 
 
1. wxapps-beta testing: Sep 23-27, 2019
 
 
 
2. wxapps-stage testing: Sep 30-Oct 4, 2019
 
|1. CMAC's
 
 
 
2. NTTO
 
|Synopsis: Aviation program changes.
 
 
 
RI Notes: NTTO are awaiting RFI submission. The aviation program has confirmed that changes are required for this RI.
 
|1. RI Planning/Scoping/Components: Aviation program changes. NTTO are awaiting RFI submission.
 
 
 
2. RI Testing: Standard RI testing process with testing starting on wxapps-beta and progressing to wxapps-stage.
 
 
 
3. RI Deployment: Standard deployment on wxapps (ops) systems. Any RTAF changes will be managed by CMAC offices.
 
 
 
4. RI Dependencies: None identified.
 
 
 
5. Risks: None identified.
 
|
 
|24.7
 
|No
 
|-
 
|​'''25.0-part1'''
 
 
 
​'''25.0-part2'''
 
|NinJo 3.4 (WPR1.5, Tsunami) + Scribe
 
|September 24, 2019 (all componenets except NinJo 3.4)
 
 
 
NinJo 3.4: October 16, 2019
 
|Next step is deployment of part1.
 
|Testing completed.
 
|Synopsis: Deployment of NinJo 3.4 (RI25.0-part2) has been delayed (given delay in dependent RI24.6-IFWUU). RI25.0-part1 (Scribe. WxO, WeatherCAN, DMS) will be deployed as scheduled
 
 
 
RI Notes:  RI25.0-part2 deployment would need to be delayed further if RI24.6 (18.04 IFW) is delayed.
 
|1. RI Planning/Scoping/Components: NinJo 3.4 MSC config release (including WPR-O Release 1.5 and deployment of Tsunami alerts in MWAS) plus changes to Scribe.
 
 
 
2. RI Testing: Testing completed.
 
 
 
3. RI Deployment: Deployment has been split into 2 parts. Part 1 of deployment will proceed with original date for all components except NinJo 3.4 (Scribe. WxO, Mobile App, DMS). Part 2 of deployment will include NinJo 3.4 (delayed until after RI24.6-IFWUU as NinJo 3.4 must be deployed on 18.04 IFW).  
 
 
 
4. RI Dependencies: NinJo 3.4 must be deployed on 18.04 IFW.
 
 
 
5. Risks:
 
 
 
- Further delays in IFWUU could continue to delay deployment of NinJo 3.4.
 
|
 
|25.0
 
|No
 
|-
 
|'''25.X'''
 
|URP 2.13.2
 
|Oct 29, 2019
 
|Package submission: Sep 30, 2019
 
 
 
1. Beta: now - Sep 30
 
 
 
2. Integration: Oct 1 - 11
 
 
 
3. UAT: Oct 14 - 25
 
|1. URP dev team
 
 
 
2. NTTO
 
 
 
3. PSD
 
|a. Removal of all decommissioned C and X-bands
 
b. Promotion of the remaining S-bands to Primary for SWP
 
|1. RI Planning/Scoping/Components: Development is on track.
 
 
 
2. RI Testing: Will be conducted on CMC urpx dev1 servers.
 
 
 
3. RI Deployment: TBD
 
 
 
4. RI Dependencies: None.
 
|
 
|25.1
 
|No
 
|-
 
|'''25.X'''
 
|IFW Desktop Box (CPU) Upgrade
 
|Starting late fall 2019
 
|TBD
 
|TBD
 
|Synopsis: Upgrade of NinJo CPU boxes to Ubuntu 18.04.
 
 
 
RI Notes: Contact project lead Krysta-Lee Clifford for information. NTTO will coordinate testing and deployment.
 
|'''1.''' RI Planning/Scoping/Components: Upgrade of NinJo CPU boxes to Ubuntu 18.04. Contact project lead Krysta-Lee Clifford for information. NTTO will coordinate testing and deployment.  '''2.''' RI Testing: Plan it to setup test box (connected to 18.04 IFW) in each office. Once test system is stable, the testing can be expanded to a live UAT which would include one box/18.04 IFW pair in each office.  
 
'''3.''' RI Deployment: May take several months to complete on all systems.
 
'''4.''' RI Dependencies: None identified.
 
|
 
|25.2
 
|No
 
|-
 
|'''25.X'''
 
|Aviation Changes
 
|December 5, 2019
 
|TBD
 
|TBD
 
|Synopsis: Aviation program changes.
 
 
 
RI Notes: NTTO are awaiting RFI submission
 
|1. RI Planning/Scoping/Components: Aviation program changes. NTTO are awaiting RFI submission.
 
 
 
2. RI Testing: Standard RI testing process with testing starting on wxapps-beta and progressing to wxapps-stage.
 
 
 
3. RI Deployment: Standard deployment on wxapps (ops) systems. Any RTAF changes will be managed by CMAC offices.
 
 
 
4. RI Dependencies: None identified.
 
 
 
5. Risks: None identified.
 
|
 
|25.3
 
|No
 
|-
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|-
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|-
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|-
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|
 
|}
 

Latest revision as of 15:14, 28 October 2019

Contents of this page have been removed and will be relocated in the near future.